VOLUME 4: BIOREMEDIATION
 

 

Quarterly and Annual Bioreactor Performance Status Reports

Bi-Annual and Annual Underground Injection Control Status Reports

Class V Underground Injection Well SWMU B-3 Bioreactor (October 2005)

Westbay Technical Memorandum (November 2005)

Class V Underground Injection Well SWMU-B3 Bioreactor (May 2006)

Construction Quality Assurance Plan, Revision One (August 2006)

SWMU B-3 Bioreactor Construction Report (February 2007)

Final SWMU B-3 Bioreactor Operation and Maintenance Manual (July 2008 Update)

Final SWMU B-3 Bioreactor Operation and Maintenance Manual (July 2010)

CSSA B-3 Extraction Well Construction Summary (September 2010)

Final DO 50 B-3 New Wells Technical Memorandum (October 2010)

 

SWMU B-3 Bioreactor Operation and Maintenance Manual (November 2010)

Operation and Maintenance Manual Update

Appendix A - TCEQ Authorization Letter

Appendix B - Product Information: Recovery Well Pumps and SymCom PumpSaver

Appendix C - Product Information: Price Pump XT150 Centrifugal Pump and Baldor Pump Model

Appendix D - Product Information: Krystil Klear Filtration Model 88 Bag Filter

Appendix E - Product Information: FullJet Standard Type G Spray Nozzles

Appendix F - Automation System Design

Appendix G - Product Information: GPI TM150 Endress+Hauser Prowhirl 72F, FT420 Flow Computer

Appendix H - Product Information: Magnetrol Liquid Level Switch Model T21 and Displacer Type, Endress+Hauser FMU40 Ultrasonic Meter, In-Situ LevelTroll 500, and Endress+Hauser WaterPilot FMX167

Appendix I - SCADA Control Components

Appendix J - Product Information: Westbay Manual

Appendix K - Field Monitoring Forms

Final SWMU B-3 Bioreactor Operation and Maintenance Manual (November 2011 Update)

B3-EXW05-LGR Installation Report (December 2012)

Final SWMU B-3 Bioreactor Operation and Maintenance Manual (December 2012 Update)

Lactate Injection Evaluation Technical Memo (January 2013)