Electrokinetic Test Report for SWMU O-1 - April 1999
Table of Contents
Section 2 - Site and Study Background
2.2 Site Background and history
2.4.2 Soil Sampling Results from Previous Investigations
Section 3 - Treatability Study Methods
3.3 Treatability Study Activities
Section 4 - Treatability Study Results and Data Evaluation
4.1.1 Initial Baseline Soil Sample Data
4.2 Laboratory Benchscale Treatability Results
4.2.1 Determination of Optimum Extractant from SWMU O-1 Soil
4.2.2 Determination of the Valence State of Chromium
4.2.3 Benchscale Electrokinetic Removal of Chromium From O-1 Soil
4.3 Field Pilot Scale Treatability Results
4.3.1 Process Operation and Monitoring
4.3.2 Chromium Contaminate Transport and Removal Observations
4.4 Investigation-Derived Waste Management Summary
Section 5 - Conclusions and Recommendations
Appendices
Appendix A Lynntech Inc. Final Technical Report and Workplan
Appendix C Field Data Sheets and Field Logbook Notes
Figures
Figure 2.2 CSSA Site Map and SWMU O-1 Location
Figure 2.3 Weapons Maintenance Process Flow Chart
Figure 2.4 Bluing Process Flow Chart
Figure 2.5 Locations of Initial Exploratory Soil Borings
Figure 2.6 Cross-Section, SWMU O-1
Figure 2.7 Anomaly Location Map, SWMU O-1
Figure 2.8 PCE Soil Gas Distribution 1995, SWMU O-1
Figure 2.9 Location of SWMU O-1 Relative to Nearby Groundwater Wells
Figure 2.10 SWMU O-1 Liner Investigation Location Map
Figure 2.11 PCE Soil Gas Distribution 1996, SWMU O-1
Figure 2.12 Initial Electrokinetic Location Excavations, SWMU O-1
Figure 2.13 Field Pilot Scale Electrokinetic System Location Map
Figure 3.1 Electrokinetic Field System Layout at SWMU O-1
Figure 4.1 Excavation of Treatment Area at SWMU O-1
Tables
Table 2.1 Liner Integrity Investigation Analytical Results
Table 2.2 1997 Initial Electrokinetic Location Investigation Analytical Results
Table 3.1 Methods of Chemical Analysis for Soil and Soil Gas Samples
Table 3.2 Methods of Geotechnical Analysis and Physical Parameters for Soil Samples
Table 3.3 1997 Treatability Study Sampling Summary
Table 4.1 1997 Electrokinetic Field Investigation Baseline Analytical Results
Table 4.2 November 1997 System Performance Analytical Results
Table 4.3 January 1998 System Performance Analytical Results
Table 4.4 Average Percentage Removal of Chromium From O-1 Soil