SWMU B-3 - Table of Contents

[Home]

[Volume 1-2]

 

SWMU B-3 Links

SWMU B-3 View Facing North - January 1999

Site Status: Open

Background

Description in Current Conditions Report (July 1999)

Chronology

Aerial Photograph

Plans (Volume 1-2)

SVE Test Work Plan (February 1996) (not available electronically)

Addendum to SVE Test Work Plan (December 1996)

RL74 and RL83 RFI Work Plan Addendum (August 1999)

Soil Vapor Extraction Work Plan, Second Addendum (December 1999)

RL17 Work Plan Amendment for Data Quality Rework (May 2000)

DO 23 Work Plan Addendum (July 2002)

Final Removal Action Report (April 2008)

Investigation Reports (Volume 3-1)

Section 4 of Technical Memorandum on Surface Geophysical Surveys, Well 16 Source Characterization (June 1995)

Section 5 of the Technical Memorandum on Soil Boring Investigation (June 1995)

Addendum to Technical Memorandum on Soil Boring Investigation (August 1995)

Section 3, Technical Memorandum on Soil Gas Surveys (June 1996)

Section 7, SWMU B-3 Characterization, Groundwater Investigation and Associated Source Characterizations Report (June 1996)

Soil Gas Survey Results, January - February 2001

SWMU B-3 Interim Remedial Action Completion Report (March 2005)

SWMU B-3 Bioreactor Construction Report (February 2007)

Final Groundwater Pumping Tests for Wells CS-MW16-LGR and CS-MW16-CC (September 2007)

Bioreactor Operations Performance Status Report, May - July 2009 (October 2009)

Final Flood Test Assessment Report (February 2010)

Biannual UIC Status Report for B-3 Bioreactor, November, 2009 - April, 2010

Biannual Bioreactor UIC Status Report (May 2010)

Bioreactor Operations Annual Performance Status Report, May - April 2010 (August 2010)

Quarter 13 Bioreactor Performance Status Report (September 2010)

Final DO 50 B-3 New Wells Technical Memorandum (October 2010)

Bioreactor UIC Status Report (November 2010)

CSSA B-3 Bioreactor Operations Annual Performance Status Report (Quarter 13 – Quarter 16, May 2010 – April 2011) (August 2011)

Final B-3 Bioreactor O&M Manual (November 2010 Update)

Bioreactor UIC Status Report (November 2010)

Final Quarter 14 Bioreactor Performance Status Report (February 2011)

CSSA B-3 Bioreactor Operations Annual Performance Status Report (Quarter 13 – Quarter 16, May 2010 – April 2011) (August 2011)

Tables

Table B3-1  Chemical Constituents Detected in Soil (March 1995)

Table B3-2  Chemical Constituents Detected in Groundwater (March 1995)

Table B3-3  Chemical Constituents Detected in Soil (February 1996)

Initial Flow Rate Setting, January 6, 2000 SWMU B-3 SVE O&M Assessment (April 2003)

TVH Estimated Levels at Initial System Settings, January 6, 2000 SWMU B-3 SVE O&M Assessment (April 2003)

Schedule of Completed O&M Activities,  SWMU B-3 SVE O&M Assessment (April 2003)

Initial Soil Gas for O&M Task and Previous Pilot Test Events, SWMU B-3 SVE O&M Assessment (April 2003)

Extraction Pressure Results and Blower Operating Parameters from Bi-weekly System Checks SWMU B-3 SVE O&M Assessment (April 2003)

Monthly Flow Rates from Individual VEWs and Main Exhaust SWMU B-3 SVE O&M Assessment (April 2003)

Field Screening Results from Monthly Soil Gas Screening Activity SWMU B-3 SVE O&M Assessment (April 2003)

VMP Field Screening Results SWMU B-3 SVE O&M Assessment (April 2003)

Analytical Results and Removal Rates for Volatile Organic Contaminants SWMU B-3 O&M Assessment (April 2003)

Comparison of Removal Rates Over Time SWMU B-3 SVE O&M Assessment (April 2003)

Contaminant Concentration in Exhaust Emissions SWMU B-3 SVE O&M Assessment (April 2003)

Water Levels in VEWs Following July 2002 Flood SWMU B-3 SVE O&M Assessment Report (April 2003)

Summary of Groundwater Sample Results from B-3 VEWs SWMU B-3 SVE O&M Assessment (April 2003)

Figures

Soil Analytical Results Map (March 1995)

Geophysical Anomaly Map (June 1995)

As-Built Expanded SVE System Layout SWMU B-3 SWMU B-3 SVE O&M Assessment (April 2003)

Water Level in VEW-01 and Daily Precipitation SWMU B-3 SVE O&M Assessment (April 2003)

Water Levels in B-3 VEWs Following July 2002 Flood SWMU B-3 SVE O&M Assessment (April 2003)

Soil Boring Logs (March 1995)

Treatability Studies (Volume 4)

Biannual Status Report Months 55 – 60 (June 2012)

Soil Vapor Extraction Test Report for SWMU B-3 (November 2001)

Soil Vapor Extraction Operations & Maintenance Report (April 2003)

Final SWMU B-3 Bioreactor Operation & Maintenance Manual (July 2008)

Class V Underground Injection Well SWMU B-3 Bioreactor (July 2006)

SWMU B-3 Bioreactor Construction Report (February 2007)

Final SWMU B-3 Bioreactor Operation & Maintenance Manual (July 2010)

CSSA B-3 Extraction Well Construction Summary (September 2010)