Solid Waste Management Unit O-1

Chronology of Actions/Investigations

Year

Month

Action/Results

Action Performed By

Project Number

1975

Unknown

Oxidation pond constructed using a vinyl plastic liner with a life expectancy of 10 years. Waste liquids and sludges from bluing operation were placed in the pond.

CSSA

NA

1984

April

Liquid and sludge sample collected from surface of pond at the request of the Texas Department of Health and taken to Brooks AFB on 20 April for evaluation. Sample was tested for metals.

TDH

Brooks AFB

NA

1985

Unknown

RRAD recommended procedure for closure of pond. Pond was filled with dirt in the fall of 1985.

RRAD

NA

1992

October

Records at CSSA reviewed during preliminary evaluation for groundwater contamination.

Parsons ES

Order 71

1995

February

EM geophysical survey performed on February 2; one anomaly found. GPR geophysical survey performed on February 15.

Parsons ES

Order 67

March

Two surface water samples collected on 3 March and analyzed for VOCs; toluene found in one sample.

Parsons ES

Chemron

Order 67

March

One surface water sample collected on 7 March and analyzed by the AL/OEB laboratory; no VOCs found in sample.

Parsons ES

AL/OEB

Order 67

March

Four soil borings (SB1-4) drilled on 14-16 March. Soil/rock samples collected on 14-16 March; VOCs found in two samples, and chromium and cadmium found in all samples.

Parsons ES

JEDI

Chemron

RL17

June

First phase of soil-gas survey performed in area of geophysical anomaly on 24-27 June; PCE found in soil-gas samples.

Parsons ES

Order 67

October

Technical presentation given on 19-20 October on groundwater investigation and source characterization actions.

CSSA

EPA

TNRCC

AFCEE

AL/OEB

Parsons ES

Orders 67 and 126

 

November

Additional surface soil sampling performed near SB2 on 15 November; PCE, chromium, and cadmium found above risk reduction standard 2 (RRS2) criteria.

Parsons ES

Chemron

Order 67

November

Five-gallon soil material sample collected for benchscale soil washing test; test performed by EET of Austin.

Parsons ES

EET

Order 67

November

Began second phase of soil gas survey on 20 November.

Parsons ES

Order 67

December

Completed second phase of soil gas survey on 5 December; PCE found in soil gas samples collected 20 November - 5 December.

Parsons ES

Order 67

December

Meeting conducted on 7 December to discuss further investigation of site, including liner investigation and benchscale testing of VOC volatilization from soils.

CSSA

AL/OEB

AFCEE

Parsons ES

Order 67

1996

January

Soil material excavation down to bedrock limestone began on 8 January for the liner integrity investigation (January-April 96). Soil samples collected from excavation and bermed soil laydown area on 8 January; PCE and chromium found in samples. Composite soil samples collected from bermed soil laydown area on 30 January; chromium found in one sample. Analytical results are in currently question due to ITS Laboratories.

AL/OEB

Parsons ES

ITS

Order 67

March

Composite soil samples collected from bermed soil laydown area on 14 March; chromium found in one sample and PCE (<1.0 mg/kg) found in both samples.

Parsons ES

ITS

Order 67

April

Soil samples collected from walls and bottom of excavated area on 11 April.

Soils within bermed laydown area placed with original excavated soils.

Liner samples collected from beneath former bermed laydown area and excavated area on 16 April; liner material classified as nonhazardous waste.

Parsons ES

ITS

Order 67

August

Additional soil gas survey performed at the site.

Parsons ES

Order 67

 

September

Surface soils sampled for hexavalent chromium (Cr(VI)) content on 4 September; no Cr(VI) found in samples.

Parsons ES

RL17

April

CSSA personnel began excavating three trenches on 11 April during initial investigation for locating field pilot scale test unit in electrokinetic treatability study.

CSSA

Parsons ES

RL17

April

Soil samples collected from trench along southeast wall of excavated area on 11 April; chromium, cadmium, lead, and zinc found in samples.

Parsons ES

ITS

RL17

April

Lynntech submitted work plan for O-1 treatability study on 28 April.

Lynntech

RL17

1997

May

Surface soil samples collected from each trench on 9 May for laboratory benchscale test in electrokinetics treatability study.

Parsons ES

Lynntech

RL17

June

Lynntech submitted revised work plan for O-1 treatability study on 10 June.

Lynntech

RL17

July

Drilling and electrokinetic well construction activities for field pilot scale test began on 7 July.

Soil samples collected from electrode wells on 8 July to establish baseline VOCs and metals contaminant concentrations and to determine extent of contamination at the site.

Parsons ES

Lynntech

RL17

August

Drilling and electrokinetic well construction activities for field pilot scale test completed on 17 August.

Parsons ES

Lynntech

RL17

September

Additional soil samples collected from electrode wells on 25 September for field pilot scale test.

Parsons ES

Lynntech

RL17

November

Additional soil samples collected from electrode wells on 6 November for field pilot scale test.

Parsons ES

Lynntech

RL17

1998

January

Final round of soil samples collected from electrode wells on 6-9 January for field pilot scale test.

Parsons ES

Lynntech

RL17

March

Lynntech submitted final technical report for O-1 Treatability Study on 25 March.

Lynntech

RL17

June

Electrokinetics treatability study data evaluation and reporting performed June-December 98.

Parsons ES

Lynntech

RL17

 

September

Surface soils sampled for hexavalent chromium (Cr(VI)) content on 4 September; no Cr(VI) found in samples.

Parsons ES

RL17

July

Lynntech submitted revised final technical report for O-1 Treatability Study on 24 July.

Lynntech

RL17

December

Electrokinetics treatability study data evaluation and reporting completed.

Parsons ES

Lynntech

RL17

December

Draft Electrokinetics Treatability Study report submitted on 4 December.

Parsons ES

RL17

1999

April

EPA memorandum indicated analytical results obtained from ITS are not usable.

EPA

NA

April

The Final Electrokinetics Treatability Study report was submitted on 30 April.

Parsons ES

RL17

November

Submitted work plan for resampling to replace analytical chemistry data generated by ITS Laboratory.

Advanced 20 soil borings (SB5-24) and collected 25 soil/rock samples for cadmium, chromium, PCE, 1,2-DCE, TCE, Vinyl Chloride, toluene and m,p-xylenes analysis.

Parsons ES

Parsons ES

O’Brien & Gere

JEDI

RL74

2000

April

Advanced 5 soil borings (SB25-29) and collected 5 soil/rock samples for cadmium, chromium, PCE, 1,2-DCE, TCE, Vinyl Chloride, toluene and m,p-xylenes analysis.

Parsons ES

O’Brien & Gere

JEDI

RL74

July

Advanced one soil borings (SB30) and collected a rock samples for cadmium, chromium, PCE, 1,2-DCE, TCE, vinyl chloride, toluene and m,p-xylenes analyses.

Parsons ES

O’Brien & Gere

JEDI

RL74

July

Contaminated soils (approximately 1,515 cubic yards) were excvated and disposed at Covel Gardens Landfill.  The area of excavation measured approximately 7,000 square feet by 5 feet deep.  Excavated area was back-filled with clay-rich soil and a 2-foot thick low-permeability clay liner was constructed over the site.

Parsons ES

Eagle

RL74

October

Interim/Stabilization Measures and Partial Facility Closure Report submitted to EPA and TNRCC.

Parsons ES

RL74

2001

December

TNRCC reviewed Interim/Stabilization Measures and Partial Facility Closure Report.

TNRCC

NA

2002

April

TNRCC letter approving SWMU O-1 closure for surface soils only.

TNRCC

NA