Environmental Cleanup Plan for AOC 65
Section 7 - Scheduling and Time Management
The AOC 65 Treatability Study project was awarded on October 1, 2001 . Modification 1 of the contract was awarded on December 21, 2001 enabled additional geophysical studies to be performed. Modification 2 increased the scope of work to include activities described in this plan and the AOC 65 Treatability Test Plan, Parsons, April 2002. A project schedule outlining the activities to be completed during the project is presented in Table 7.1.