Solid Waste Management Unit Building 43

Chronology of Actions/Investigations

Year

Month

Action/Results

Action Performed By

Project Number

Unknown

Unknown

Inactive makeshift ammunition demolition facility was used to burn miscellaneous solid waste and ammunition. The area adjacent to Building 43 is covered with molten metal and spent ammunition.

CSSA

NA

1995

July

Soil gas survey completed on July 19 between SWMUs B-3 and B-4 included SWMU Bldg. 43 area; however, the soil gas survey grid was spaced at every 100 ft. Bldg. 43 is only approximately 20 by 25 feet, so the soil gas survey interval was not adequate to characterize the Bldg. 43 site; however, TCE was detected in one soil gas sample at the Building 43 site.

Parsons ES

Order 67

1996

February

Work Plan for Building 43 Investigation was submitted.

Parsons ES

RL17

March - April

EM geophysical survey performed on March 13 and April 2; one geophysical anomaly found that was not related to suspected waste management activities.

Parsons ES

RL17

1997

August

Surface of site was swept by UXB for UXO on August 28. No UXO was found, only surface debris.

Parsons ES
UXB

RL33

1998

March

Addendum to Work Plan submitted for additional investigation at Building 43.

Parsons ES

RL53

2000

February - March

Advanced 6 soil borings (SB1-6) and collected 18 soil/rock samples for VOCs, SVOCs, metals and explosives (3 samples) and VOCs, metals and explosives (15 samples) for analysis.

Parsons ES

APPL, Inc.

Data Chem

RL53

2001

March

One wipe sample was collected from the Bldg. 43 burn box and analyzed for dioxins and furans.  No dioxins or furans were detected above their RLs.

Parsons

RL53

2002

December

Final RCRA Facility Investigation Report

submitted.

Parsons

RL53

2003

March

Ten additional surface soil samples collected for metals analysis in an effort to define horizontal extent of contamination.

Parsons

APPL, Inc.

RL17

June

Final RCRA Facility Investigation Report Addendum submitted.

Parsons

RL17

December

Final TO 0019 Work Plan Addendum submitted.

Parsons

TO19

2004

July

Excavated soil around building.  Confirmation and waste characterization samples collected.

Parsons

TO19

November - December

Excavated soil hauled off and building demolished.

Parsons

TO19

2005

January

Approximately 100 cu. yds. of soil treated with PIMS.  Scrapped up another 300 cu. yds. of soil from the surface.

Parsons

TO19

February - March

Hauled out excavated soils to Covel Gardens. Collected confirmation samples from sidewalls and bottom surface of excavation.

Parsons

TO19

April

Final RCRA Facility Investigation Closure Report

submitted.

Parsons

TO19

August

Closure approved by TCEQ.

TCEQ

NA