Solid Waste Management Unit B-10

Chronology of Actions/Investigations

Year

Month

Action/Results

Action Performed By

Project Number

Unknown

Unknown

Site utilized as an ammunition disposal area.

CSSA

NA

1995

July

Performed soil gas survey in "area between B-3 and B-4," which includes B-10; detected PCE.

CSSA

NA

1996

February

Work Plan for B-10 investigation submitted.

Parsons ES

RL17

1996

March

Geophysical survey performed on March 14. One anomaly associated with non-waste management activities was found.

Parsons ES

RL17

1996

April

Additional geophysical survey performed on April 2 for verification of site features.

Parsons ES

RL17

1996

August

Performed soil gas survey at B-10; detected PCE in all samples.

Parsons ES

RL17

1997

August

UXO surface sweep and partial trench excavation conducted. Results indicated that there are either two small trenches or one large one.

Parsons ES
UXB

RL33

1998

March

Addendum to Work Plan submitted.

Parsons ES

RL53

2003

May

Final RCRA Facility Investigation/Closure Report submitted to TCEQ.

Parsons

RL17

2004

January

Closure approved by TCEQ.

Parsons

RL53