Spill Prevention, Control, and Countermeasures Plan and Installation Spill Contingency Plan
Table 2.1 - Summary of Potential Spill Scenarios and Flow Direction
Category |
Spill Source |
Contents |
Potential Types of Failure |
Volume |
Rate of Flow (gal/hour) |
Flow Direction |
Containment |
ASTs |
Bldg. 99 AST |
Diesel |
Catastrophic failure - e.g., collision from heavy equipment
Internal explosion
Rupture of tank or piping Slow leak of tank or piping, e.g., due to rust or corrosion |
500 gal. |
500 or more |
South, over land to unnamed drainage to Leon Creek |
Double-wall tanks |
Bldg. 4 AST |
Diesel |
1,000 gal. |
1,000 or more |
South to overland drainage to Leon Creek |
|||
Bldg. 46 AST |
Diesel |
1,000 gal. |
1,000 or more |
East towards Salado Creek |
|||
Bldg. 201 AST |
Diesel |
2,000 gal. |
1,000 or more |
Southeast toward Salado Creek |
|||
Bldg. 4 AST |
Gasoline |
10,000 gal. |
1,000 or more |
South to overland drainage to Leon Creek |
|||
Tanker Truck Loading/Unloading Operations |
Fuel delivery or oil recycling tanker truck |
Diesel, gasoline, oil |
Catastrophic failure - e.g., collision
Internal explosion
Rupture or failure of truck during AST filling
Failure to properly connect or disconnect delivery hose |
to 9,000 gal. |
5,000 or more (worst case) |
See above for specific ASTs |
Absorbent spill pads and booms on CSSA tanker truck escort |
Other Equipment/Storage |
Bldg. 90 |
Petroleum Naptha |
Rupture or leak |
15 - 177 gal. |
N/A |
Containment pallets |
|
Volatile Corrosive Inhibitor |
120 gal. |
||||||
Nickel penetrate (liquid) |
30 gal. |
||||||
Nickel penetrate (crystal) |
55 gal. |
N/A |
Crystal would be swept up and disposed of properly. |