Addendum to SVE Test Work Plan for SWMU B-3
Table 5.1 - Proposed Schedule for Expanded Pilot Study
Task | Begin Date | Completion Date |
1. Addendum preparation | ||
Draft | October 14, 1996 | November 1, 1996 |
AFCEE/CSSA review | November 1, 1996 | November 18, 1996 |
Final | November 18, 1996 | December 23, 1996 |
2. Subcontracting | November 18, 1996 | December 23, 1996 |
3. Confirmation Sampling | December 26, 1996 | December 27, 1996 |
4. Install VEWs | December 279, 1996 | January 3, 19970 |
5. Initial System Check | January 6, 1997 | January 7, 1996 |
6. Hydrocarbon Recovery Test | January 7, 1997 | February 4, 1997 |
7. Multiple Configuration Test | ||
First | February 5, 1997 | March 5, 1997 |
Second | April 7, 1997 | April 21, 1997 |
Third | May 21, 1997 | June 4, 1997 |
8. Design Install Automation | June 4, 1997 | June 13, 1997 |
9. Prepare Technical Report | ||
Draft | June 16, 1997 | August 1, 1997 |
CSSA/AFCEE review | August 4, 1997 | September 25, 1997 |
Final | September 8, 1997 | October 8, 1997 |