Area of Concern 67

Chronology of Actions/Investigations

Year

Month

Action/Results

Action
Performed By

Project
Number

Unknown

Unknown

Area includes the concrete pad that sat under a 1250 gallon above ground storage tank and a ditch, located east of Building 90-1 (bluing shop). The tank contained rinsate from floor cleaning activities and was removed in approximately 1997.

CSSA

NA

2001

January-February

Soil gas survey performed, testing for TCE, PCE, cis-1,2-DCE, trans-1,2-DCE, BTEX, vinyl chloride, toluene, o-xylene, m,p-xylene and benzene. No VOCs detected within the boundaries of AOC 67.

Parsons

DO 5084

2001

April

Soil borings completed and samples collected (SB01 � SB03). Lead and chromium samples exceeded background levels.

Parsons

DO 5084

2002

October

Final RCRA Facility Investigation Report submitted.

Parsons

DO 5084

2003

December

Final TO 0019 Work Plan Addendum submitted.

Parsons

TO19

2004

February - May

Excavated soils along drainage ditch and removed concrete slab.

Collected 5 samples for VOCs and metals (Ba, Cu, Pb, Cr, and Zn). Waste characterization samples collected.

Excavated soil hauled off-post to Covel Gardens.

Parsons

TO19

2007

December

Excavated additional soil from drainage ditch. Approximately 50-60 CY of material were excavated from both AOC-67 and AOC-68.

Additional waste characterization and confirmation samples collected.

Parsons

DO11

2008

 

February

Excavated approximately 2 CY of material was excavated during this event.  Excavated material from this event was taken off post with material generated from the 2007 excavation event at AOC‑67 and with the initial excavation and removal activities at AOC‑68. 

Parsons

DO11

April

Final confirmation samples collected at two trench locations.

Parsons

DO11

2010

 

May

Release Investigation Report submitted to TCEQ.

Parsons

DO11

September

Closure of AOC-67 and AOC-68 approved by TCEQ.

TCEQ

NA