Year |
Month |
Action/Results |
Action
Performed By |
Project
Number |
Unknown |
Unknown |
Area
consisting of three barrels with rocks in them.
Located south of deer stand 41 in the East Pasture, and southwest
of the road intersection. |
CSSA |
NA |
2001 |
January- February |
Two soil gas survey samples were collected and analyzed for chlorinated and aromatic volatile organics. No target VOC compounds were detected. |
Parsons |
DO 5084 |
2004 |
October |
Excavated slit trenches across the site, found only a rock trench, suspect it may be a leachate field. |
Parsons |
DY01 |
2006 |
December |
Reviewed aerial photographs for visual indication of site activity. An area with denuded vegetation can be seen in a 1957 photo. |
Weston |
NA |
2007
|
February - March |
Conducted electromagnetic geophysical survey and exploratory trenching to investigate the potential presence of buried materials. A total of 12 discrete soil samples were collected form five of the six trench locations and submitted for laboratory analysis. |
Weston |
NA |
May |
Presented results of geophysical survey and trenching investigation at a meeting with USEPA and TCEQ representatives. |
Weston |
NA |
|
June |
Re-sampled three of the trench locations investigated in March 2007, including those locations with the highest reported benzene concentrations. |
Weston |
NA |
|
July |
Conducted an informal reconnaissance survey to look for potential sources of low VOC and SVOC concentrations observed at site. |
Weston |
NA |
|
September |
Proposed parameters for calculating a Tier 2 soil-to-groundwater PCL for benzene were discussed during a quarterly Technical Interchange Meeting with representatives from CSSA, USEPA, and TCEQ. |
Weston |
NA |
|
December |
Conducted sampling to obtain vertical delineation of benzene-impacted soil. Trenches were excavated at locations with benzene concentrations exceeding the Tier 1 PCL. |
Weston |
NA |
|
2008 |
August |
Final Affected Property Assessment Report for AOC-63 submitted. |
Weston |
NA |
2009
|
February |
TCEQ requested additional information in order to approve closure of AOC-63. |
TCEQ |
NA |
July |
TCEQ |
NA |
||
2010 |
August |
TCEQ |
NA |