Project
Number |
1995 |
May |
Geophysical
survey was conducted at all the “open” areas within a 2,000-foot
radius of well 16, including AOC 42.
Found four anomalies. Anomaly
A may be associated with the trash pile present in the same area, and has
been designated as AOC 62. Anomalies B, C, and D may be additional
trenches due to their proximity to other trenches, and have been
designated as AOC 42. |
Parsons
ES |
Order
67 |
June-July |
Fourteen
soil-gas survey samples collected and analyzed for chlorinated and
aromatic volatile organics. PCE was the only target analyte detected. |
|
Order 67 |
|
2010 |
December |
Completed XRF survey of 16 locations |
Parsons |
NA |
2011 |
March |
Completed excavation, collected confirmation and waste characterization samples. |
Parsons |
NA |
April |
Collected additional samples – results clean. |
Parsons |
NA |
|
August |
Release Investigation Report submitted to TCEQ |
Parsons |
NA |
|
December |
TCEQ |