Area of Concern 50

Chronology of Actions/Investigations

Year

Month

Action/Results

Action Performed by

Project Number

1996

March

Nickel penetrate site located approximately 100 feet from SWMU B-30. 

Parsons ES

RL17

1999

December

Collected 2 surface samples (SS1-2) and analyzed for TCLP metals.

Parsons ES

O’Brien & Gere

DO5068

2000

December

Conducted EM and GPR surveys.

Parsons ES

DO 5068

2001

March 

Excavated nickel penetrate from top of soil surface. Discovered waste trench.

Parsons ES

DO 5068

April 

Finished excavation of nickel penetrate and waste trench. Collected soil samples from bottom of trench.

Parsons ES

DO 5068

August

Collected ten post-excavation soil samples.

Parsons ES

DO 5068

2002

December

RCRA Facility Investigation Report submitted to TCEQ.

Parsons 

DO 5068

2003

December

Final TO 0019 Work Plan Addendum submitted.

Parsons

TO19

2004

January

Began site excavation. Removed approximately 1 foot of soil from surface of site. Closure and waste characterization samples collected.

Parsons

TO19

February - May

Excavated areas where closures samples failed. Hauled excavated soil off-post to Covel Gardens.

Parsons

TO19

June - July

Backfilled excavated area.

Parsons

TO19

2005

 

February

Final RFI Closure Report submitted

Parsons

TO19

April

Closure approved by TCEQ.

TCEQ

NA