This 18th quarterly progress report for Camp Stanley Storage Activity (CSSA), Texas, U.S. Environmental Protection Agency (EPA) Identification Number TX2210020739, is submitted in accordance with the Administrative Order on Consent (Order) issued to CSSA on May 5, 1999, pursuant to §3008(h) of the Safe Drinking Water Act (SDWA), as amended by Resource Conservation and Recovery Act (RCRA), and further amended by the Hazardous and Solid Waste Act (HSWA) of 1984, 42 U.S.C. §6928(h). This report addresses the project progress from August 1, 2003, through October 31, 2003 (Quarter 18). Subsequent progress reports will continue to be submitted on a quarterly basis.
This report details work completed on tasks associated with the four project phases outlined in the Order. Phase names and task names listed below are taken directly from the Order. Information requested in the Order for each active task is provided in this report. If the task is not yet active, that is also noted.
Task I |
Interim/Stabilization Measures (I/SM) Work Plan (WP) |
Task II |
I/SM Implementation |
Task III |
Reports |
Task I |
Preliminary Report: Description of Current Conditions (DCC) |
Task II |
RCRA Facility Investigation (RFI) WP |
Task III |
Facility Investigation |
Task IV |
Human Health and Ecological Risk Assessment |
Task V |
Investigation Analysis |
Task VI |
Treatability Studies |
Task VII |
Progress Reports |
Task VIII |
Identification and Development of Corrective Action Alternatives |
Task IX |
Evaluation of Corrective Measures Alternatives |
Task X |
Reports |
Corrective Measures Implementation
Task XI |
Corrective Measure Implementation (CMI) Program Plan |
Task XII |
Corrective Measure Design |
Task XIII |
Corrective Measure Construction |
Task XIV |
Reports |
Details of the evaluation of the percent complete by task are included as Table 1. An updated project team chart along with telephone numbers and addresses are included as Table 2. The Project Financial Information Summary and the Percentage of Funds Expended, which is required every third progress report, is included as Attachment 1 in this quarterly report for Quarter 18. Attachment 2 includes the figures referenced in this report. A summary of the status of all identified Solid Waste Management Units (SWMUs) and Areas of Concern (AOCs) present at CSSA is provided in Attachment 3.