Project Number | Description of Task | Relation to Order | Percent Complete |
DO23 | Project Management | RFI | 100% |
| Plan Addenda | RFI | 100% |
| Meetings | RFI | 100% |
| Sampling/Analysis | RFI | 100% |
| Well Upgrades | RFI | 100% |
| Well Installations | RFI | 100% |
| Hazardous Waste Management | RFI | 100% |
RL17 | RFI Scoping | RFI | 100% |
| Site Characterization | RFI | 90% |
| Treatability Investigations | RFI | 100% |
| Sampling and Analysis | RFI | 100% |
| Site Work and Utilities | RFI | 100% |
| Meeting Minutes Preparation | RFI | 100% |
| Presentation Materials | RFI | 100% |
| Letter Report Preparation | RFI | 100% |
| Project Management | RFI | 97% |
| Integrated Waste Management/Spill Plan | NA | 100% |
| Program Management | RFI | 85% |
RL33 | Project Management | RFI | 100% |
| Meetings | RFI | 100% |
| Project Plans | RFI | 100% |
| GIS | RFI | 100% |
| Site Investigations/UXO Clearance | RFI | 100% |
| B-20 Treatability Studies | RFI | 100% |
| IDW Management | RFI | 100% |
| Program Management | RFI | 100% |
RL53 | Project Management | RFI | 95% |
| Site Characterizations | RFI | 90% |
| Groundwater Wells | RFI | 100% |
| Sampling and Analysis | RFI | 90% |
| GIS | RFI | 98% |
| Project Plans | RFI | 100% |
| Meetings | RFI | 100% |
| Background Evaluation | RFI | 100% |
| Program Management | RFI | 93% |
RL74 | Project Management | IM/RFI | 97% |
| Meetings | IM/RFI | 100% |
| Groundwater Monitoring | IM | 99% |
| Pump Installation | RFI | 15% |
| SVE O&M | RFI | 100% |
| Plans | RFI | 100% |
| Current Conditions Report | RFI | 100% |
| O-1 Interim Measures | IM | 99% |
| H Order Support | IM/RFI | 65% |
| Building 40 Sampling | RFI | 93% |
| GIS and Web Site | IM/RFI | 94% |
| IDW Management | RFI | 100% |
| Groundwater Modeling | RFI | 5% |
| Encyclopedia Updates | RFI | 100% |
| Laboratory Audit | IM/RFI | 100% |
| Off-post Well Sampling | IM | 100% |
| Additional Rounds of Groundwater Monitoring | IM/RFI | 100% |
| Program Management | RFI | 98% |
RL83 | Project Management | IM/RFI | 98% |
| Meetings | IM/RFI | 75% |
| Well Research and Mapping | RFI | 100% |
| Hydrogeologic Conceptual Model | RFI | 80% |
| B-3 SVE O&M | RFI | 80% |
| Risk Assessment CSM | RFI | 80% |
| Cluster Well Installations | RFI | 95% |
| Quarterly Progress Reports | IM/RFI | 100% |
| SWMU/AOC Investigations | RFI | 95% |
| Soil Pile Disposition Assessment | IM | 80% |
| Encyclopedia Updates | IM/RFI | 95% |
| Title V Non-Applicability Demonstration | NA | 100% |
| SPCC Plan Update | NA | 100% |
| TPDES Permit Update | NA | 100% |
| Laboratory Audit | IM/RFI | 80% |
| GIS Enhancements and Database Updates | IM/RFI | 90% |
| Groundwater Monitoring | IM/RFI | 40% |
| CRP | RFI | 100% |
| Program Management | IM/RFI | 75% |
DO5068 | DO Management and Meetings | IM/RFI | 93% |
| Geophysics and Drilling | RFI | 100% |
| Surface Sampling | RFI | 100% |
| Soil Gas Surveys | RFI | 100% |
| AOC-50 Interim Measures | IM/RFI | 100% |
| WPs and Reporting | RFI | 81% |
DO5084 | DO Management and Meetings | IM/RFI | 75% |
| AOC-65 Phase II RFI | RFI | 100% |
| Soil Gas Surveys | RFI | 100% |
| AOC-67 Phase II RFI | RFI | 100% |
| On-post Groundwater Monitoring | IM/RFI | 100% |
| Off-post Groundwater Monitoring | IM/RFI | 100% |
| PIMS Study | IM | 100% |
| LAN Support | NA | 90% |
| Drought Contingency Plan | NA | 69% |
| CRP Updates | RFI | 90% |
| Lab Audit | IM/RFI | 85% |
| Aerial Photography | NA | 90% |
| Quarterly Reports | IM/RFI | 80% |
TO 0042 | TO Management | IM/RFI | 41% |
| Meetings | IM/RFI | 25% |
| Site Survey/WPs | IM/RFI | 100% |
| New Well Installation/Well Upgrade | RFI | 46% |
| On-post Groundwater Monitoring | IM/RFI | 40% |
| Analytical Validation | RFI | 27% |
| Information Management Systems | RFI | 19% |
| Off-post Groundwater Monitoring | IM/RFI | 0% |
TO 0058 | TO Management | IM/RFI/TS | 54% |
| Meetings | IM/RFI/TS | 51% |
| Building 90 Removal Action | IM/HEA | 64% |
| Treatability Study | RFI/TS | 65% |
| Treatability Study Report and Technology Evaluation | RFI/TS | 4% |
TO 0079 | Project Management | IM/RFI | 0% |
| Meetings | RFI | 0% |
| Environmental Encyclopedia Updates | RFI | 0% |
| LAN Support | NA | 0% |
| Quarterly Progress Reports | IM/RFI | 0% |
TO 0009 | Delivery order management | IM/RFI | 0% |
| Technical plans | RFI | 0% |
| Field Work | RFI | 0% |
| Technical Reports | RFI | 0% |
| Meeting support | RFI | 0% |
DO 0023 | Project Management |
| 60% |
| Project Plans |
| 100% |
| RFI Field Work |
| 100% |
| Laboratory & Data Management |
| 45% |
| RFI Report |
| 100% |
| IRA |
| 50% |
| IRA Report |
| 0% |
| Technology Evaluation |
| 40% |
| Environmental Management System |
| 0% |
| Community Relations |
| 100% |
| Proposal Preparations |
| 100% |