12th Quarter - Final Quarterly Progress Report
Attachment 1 - Overall (H) Order Percent Complete
Task Name | % of Project | % of Phase | % Complete | % of Activity Complete | % of Task Complete |
Interim Measures | 30% | 46.8% | |||
Interim Measures Work Plan | 7% | 100% | 7.0% | ||
Interim Measures Implementation | 70% | 37% | 25.7% | ||
Reports | 23% | 61% | 14.1% | ||
RCRA Facility Investigation | 30% | 41.4% | |||
Preliminary Report | 5% | 100% | 5% | ||
RFI Workplan | 10% | 99% | 10% | ||
Facility Investigation | 45% | 26% | 12% | ||
Risk Assessment | 15% | 14% | 2% | ||
Investigation Analysis | 10% | 27% | 3% | ||
Treatability Studies | 10% | 93% | 9% | ||
Progress Reports | 5% | 10% | 0% | ||
Corrective Measures Study | 10% | 0% | |||
Identify and Develop Alternatives | 15% | 0% | 0% | ||
Evaluate Alternatives | 60% | 0% | 0% | ||
Reports | 25% | 0% | 0% | ||
Corrective Measures Implementat | 30% | 0% | |||
Implementation Program Plan | 5% | 0% | 0% | ||
Corrective Measure Design | 15% | 0% | 0% | ||
Corrective Measure Construction | 70% | 0% | 0% | ||
Reports | 10% | 0% | 0% | ||
| |||||
% of Phase Complete | 26.45% |