Task Name

% of Project

% of Phase

% Complete

% of Activity Complete

% of Task Complete

Interim Measures

30%

41.1%

Interim Measures Work Plan

7%

100%

7.0%

 

Interim Measures Implementation

70%

29%

20.2%

 

Reports

 

23%

60%

13.8%

 

RCRA Facility Investigation

30%

38.9%

Preliminary Report

5%

100%

5%

 

RFI Workplan

10%

99%

10%

 

Facility Investigation1

45%

21%

10%

 

Risk Assessment

15%

14%

2%

 

Investigation Analysis

10%

27%

3%

 

Treatability Studies

10%

93%

9%

 

Progress Reports

 

5%

7%

0%

 

Corrective Measures Study

10%

0%

Identify and Develop Alternatives

15%

0%

0%

 

Evaluate Alternatives

60%

0%

0%

 

Reports

 

25%

0%

0%

 

Corrective Measures Implementation

30%

0%

Implementation Program Plan

5%

0%

0%

 

Corrective Measure Design

15%

0%

0%

 

Corrective Measure Construction

70%

0%

0%

 

Reports

10%

0%

0%

 

 

         
     

% of Phase Complete

 

24.00%