Table 1 - Project Tasks Completion to Date
(values updated through March 20, 2001)
Project Number | Description of Task | Relation to Order | Percent Complete |
DO23 | Project Management | RFI | 97%* |
| Plan Addenda | RFI | 100% |
| Meetings | RFI | 82% |
| Sampling/Analysis | RFI | 95% |
| Well Upgrades | RFI | 96% |
| Well Installations | RFI | 76% |
| Hazardous Waste Management | RFI | 100% |
RL17 | RFI Scoping | RFI | 100% |
| Site Characterization | RFI | 70% |
| Treatability Investigations | RFI | 96% |
| Sampling and Analysis | RFI | 91% |
| Site Work and Utilities | RFI | 100% |
| Meeting Minutes Preparation | RFI | 100% |
| Presentation Materials | RFI | 95% |
| Letter Report Preparation | RFI | 100% |
| Project Management | RFI | 92% |
| Integrated Waste Management/Spill Plan | NA | 100% |
| Program Management | RFI | 92% |
RL33 | Project Management | RFI | 95% |
| Meetings | RFI | 75% |
| Project Plans | RFI | 100% |
| GIS | RFI | 100% |
| Site Investigations and UXO Clearance | RFI | 87% |
| B-20 Treatability Studies | RFI | 95% |
| IDW Management | RFI | 0% |
| Program Management | RFI | 95% |
RL53 | Project Management | RFI | 89% |
| Site Characterizations | RFI | 70% |
| Groundwater Wells | RFI | 100% |
| Sampling and Analysis | RFI | 93% |
| GIS | RFI | 95% |
| Project Plans | RFI | 100% |
| Meetings | RFI | 75% |
| Background Evaluation | RFI | 95%* |
| Program Management | RFI | 88% |
RL74 | Project Management | IM/RFI | 91% |
| Meetings | IM/RFI | 66% |
| Background Evaluation | RFI | 95%* |
| Program Management | RFI | 88% |
RL74 | Project Management | IM/RFI | 91% |
| Meetings | IM/RFI | 66% |
| Groundwater Monitoring | IM | 98% |
| Pump Installation | RFI | 0% |
| SVE Operations & Maintenance | RFI | 98% |
| Plans | RFI | 100% |
| Current Conditions Report | RFI | 100% |
| O-1 Interim Measures | IM | 95%* |
| H Order Support | IM/RFI | 65% |
| Building 40 Sampling | RFI | 55% |
| GIS and Web Site | IM/RFI | 65% |
| IDW Management | RFI | 10% |
| Groundwater Monitoring | IM | 5% |
| Encyclopedia Updates | RFI | 100% |
| Laboratory Audit | IM/RFI | 100% |
| Off-site Well Sampling | IM | 100% |
| Additional Rounds of Groundwater Monitoring | IM/RFI | 75% |
| Program Management | RFI | 76% |
RL83 | Project Management | IM/RFI | 88% |
| Meetings | IM/RFI | 42% |
| Well Research and Mapping | RFI | 98% |
| Hydrogeologic Conceptual Model | RFI | 7% |
| B-3 SVE Operations & Maintenance | RFI | 70% |
| Risk Assessment Conceptual Site Model | RFI | 80% |
| Cluster Well Installations | RFI | 50% |
| Quarterly Progress Reports | IM/RFI | 88% |
| SWMU and AOC Investigations | RFI | 65% |
| Soil Pile Disposition Assessment | IM | 40% |
| Encyclopedia Updates | IM/RFI | 60% |
| Title V Non-applicability Demonstration | NA | 97% |
| SPCC Plan Update | NA | 98% |
| TPDES Permit Update | NA | 100% |
| Laboratory Audit | IM/RFI | 80% |
| GIS Enhancements and Database Updates | IM/RFI | 60% |
| Groundwater Monitoring | IM/RFI | 1% |
| Community Relations Plan | RFI | 100% |
| Program Management | IM/RFI | 56% |
DO 5068 | DO Management and Meetings | IM/RFI | 55% |
| Geophysics and Drilling | RFI | 85% |
| Surface Sampling | RFI | 85% |
| Soil Gas Surveys | RFI | 100% |
| AOC 50 Interim Measures | IM/RFI | 80% |
| Work Plans and Reporting | RFI | 48% |
DO5084 | DO Management and Meetings | IM/RFI | 14% |
| AOC 65 Phase II RFI | RFI | 28% |
Soil Gas Surveys | RFI | 84% | |
AOC 67 Phase II RFI | RFI | 25% | |
On-site Groundwater Monitoring | IM/RFI | 0% | |
Off-site Groundwater Monitoring | IM/RFI | 0% | |
PIMS Study | IM | 50% | |
LAN Support | NA | 10% | |
Drought Contingency Plan | NA | 70% | |
Community Relations Plan Update | RFI | 0% | |
| Lab Audit | IM/RFI | 0% |
| Aerial Photography | NA | 0% |
| Quarterly Reports | IM/RFI | 3% |
* Reduced due to extension of project. |