7th Quarterly Progress Report

Overall (H) Order Percent Complete

Task Name

% of Project

% of Phase

% Complete

% of Activity Complete

% of Task Complete

Interim Measures

30%

36.7%

Interim Measures Work Plan

7%

100%

7.0%

 

Interim Measures Implementation

70%

28%

19.6%

 

Reports

 

23%

44%

10.1%

 

RCRA Facility Investigation

30%

37.2%

Preliminary Report

5%

100%

5%

 

RFI Workplan

10%

99%

10%

 

Facility Investigation1

45%

18%

8%

 

Risk Assessment

15%

14%

2%

 

Investigation Analysis

10%

23%

2%

 

Treatability Studies

10%

93%

9%

 

Progress Reports

 

5%

6%

0%

 

Corrective Measures Study

10%

0%

Identify and Develop Alternatives

15%

0%

0%

 

Evaluate Alternatives

60%

0%

0%

 

Reports

 

25%

0%

0%

 

Corrective Measures Implementation

30%

0%

Implementation Program Plan

5%

0%

0%

 

Corrective Measure Design

15%

0%

0%

 

Corrective Measure Construction

70%

0%

0%

 

Reports

10%

0%

0%

 

 

     

% of Phase Complete

 

22.19%