Task Name |
% of Project |
% of Phase |
% Complete |
% of Activity Complete |
% of Task Complete |
Interim Measures |
30% |
36.7% |
|||
Interim Measures Work Plan |
7% |
100% |
7.0% |
||
Interim Measures Implementation |
70% |
28% |
19.6% |
||
Reports |
|
23% |
44% |
10.1% |
|
RCRA Facility Investigation |
30% |
37.2% |
|||
Preliminary Report |
5% |
100% |
5% |
||
RFI Workplan |
10% |
99% |
10% |
||
Facility Investigation1 |
45% |
18% |
8% |
||
Risk Assessment |
15% |
14% |
2% |
||
Investigation Analysis |
10% |
23% |
2% |
||
Treatability Studies |
10% |
93% |
9% |
||
Progress Reports |
|
5% |
6% |
0% |
|
Corrective Measures Study |
10% |
0% |
|||
Identify and Develop Alternatives |
15% |
0% |
0% |
||
Evaluate Alternatives |
60% |
0% |
0% |
||
Reports |
|
25% |
0% |
0% |
|
Corrective Measures Implementation |
30% |
0% |
|||
Implementation Program Plan |
5% |
0% |
0% |
||
Corrective Measure Design |
15% |
0% |
0% |
||
Corrective Measure Construction |
70% |
0% |
0% |
||
Reports |
10% |
0% |
0% |
||
|
|||||
% of Phase Complete |
22.19% |