Task Name |
% of Phase |
% of Task |
% Complete |
% of Activity Complete |
% of Activity Remaining |
% of Task Complete |
Comments/Status |
|
1 |
Interim Measures Work Plan |
7% |
100.0% |
|||||
|
Draft IM Workplan |
80% |
100% |
80% |
0% |
|||
|
Draft Final IM Workplan |
15% |
100% |
15% |
0% |
|||
|
Final IM Workplan |
5% |
100% |
5% |
0% |
|||
2 |
Interim Measures Implementation |
70% |
28.0% |
|||||
Sample 3 Off-Site Wells |
2% |
100% |
2% |
0% |
|
|||
Sample 20 Off-Site Wells (6 events) |
10% |
0% |
0% |
100% |
Complete when 6 rounds of off-site sampling (20 wells) done. |
|||
Locate and map off-site wells |
2% |
95% |
2% |
5% |
Complete when final map is submitted. In progress. |
|||
O-1 Soil Borings |
5% |
100% |
5% |
0% |
||||
O-1 Excavation, Stabilization, Diposal |
18% |
100% |
18% |
0% |
||||
Establish Treatment Unit |
2% |
0% |
0% |
100% |
Treatment unit may or may not be necessary. |
|||
Determine appropriate disposition of soil piles |
11% |
10% |
1% |
90% |
Complete when treatability studies results have been evaluated. |
|||
Treat soil piles |
45% |
0% |
0% |
100% |
Unfunded CSSA future work. |
|||
AOC 50 Excavatiopn and Disposal |
5% |
0% |
0% |
100% |
Not included as IM in the Order. |
|||
3 |
Reports |
23% |
44.0% |
|||||
|
Quarterly Progress Report 1 (August 1999) |
0.57% |
100% |
0.57% |
0% |
|||
|
Quarterly Progress Report 2 (November 1999) |
0.57% |
100% |
0.57% |
0% |
|||
|
Quarterly Progress Report 3 (February 2000) |
0.57% |
100% |
0.57% |
0% |
|||
|
Quarterly Progress Report 4 (May 2000) |
0.57% |
100% |
0.57% |
0% |
|||
|
Quarterly Progress Report 5 (August 2000) |
0.57% |
100% |
0.57% |
0% |
|||
|
Quarterly Progress Report 6 (November 2000) |
0.57% |
100% |
0.57% |
0% |
|||
|
Quarterly Progress Report 7 (February 2001) |
0.57% |
100% |
0.57% |
0% |
|||
|
Quarterly Progress Report 8 (May 2001) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 9 (August 2001) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 10 (November 2001) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 11 (February 2002) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 12 (May 2002) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 13 (August 2002) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 14 (November 2002) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 15 (February 2003) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 16 (May 2003) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 17 (August 2003) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 18 (November 2003) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 19 (February 2004) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 20 (May 2004) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 21 (August 2004) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 22 (November 2004) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 23 (February 2005) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 24 (May 2005) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 25 (August 2005) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 26 (November 2005) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 27 (February 2006) |
0.57% |
0% |
0% |
100% |
|||
|
Quarterly Progress Report 28 (May 2006) |
0.57% |
0% |
0% |
100% |
|||
|
Draft O-1 IM Report |
25% |
100% |
25% |
0% |
|||
|
Draft final O-1 IM Report |
10% |
100% |
10% |
0% |
|||
|
Final O-1 IM Report |
5% |
100% |
5% |
0% |
|||
|
Draft Soil Pile IM Report |
30% |
0% |
0% |
100% |
Complete when report submitted. |
||
|
Draft Final Soil Pile IM Report |
10% |
0% |
0% |
100% |
Complete when report submitted. |
||
Final Soil Pile IM Report |
4% |
0% |
0% |
100% |
Complete when report submitted. |
|||
% of Phase Complete |
36.72% |