[Home] [Master Table of Contents]
[Quarterly Progress Reports Index]
6th Quarter - Final Quarterly Progress Report
August 1, 2000 - October 31, 2000
Table of Contents
This quarterly progress report for CSSA, Texas, U.S. EPA Identification Number TX2210020739, is submitted in accordance with the Administrative Order on Consent (Order) issued to CSSA on May 5, 1999 pursuant to §3008(h) of the Solid Waste Disposal Act, as amended by RCRA, and further amended by the Hazardous and Solid Waste Amendments of 1984, 42 U.S.C. §6928(h). This report encompasses the fifth progress report period for the project and includes progress on the project from August 1, 2000 through October 31, 2000 (Quarter 6). Subsequent progress reports will continue to be submitted on a quarterly basis.
This report details work completed on tasks associated with four project phases outlined in the order. Phase names and task names listed below are taken directly from the Order. For each active task, the information requested in the Order is provided in this report. If the task is not yet active, that is also noted.
Task I - Interim/Stabilization Measures Work Plan
Task II - Interim/Stabilization Measures Implementation
Task I - Preliminary Report: Description of Current Conditions
Task III - Facility Investigation
Task IV - Human Health and Ecological Risk Assessment
Task V - Investigation Analysis
Task VI - Treatability Studies
Task VIII - Identification and development of Corrective Action Alternatives
Task IX - Evaluation of Corrective Measures Alternatives
Corrective Measures Implementation
Task XI - Corrective Measure Implementation Program
Task XII - Corrective Measure Design
Task XIII - Corrective Measure Construction
Attachment 1 - Fiscal Report through September 2000
Table 2 - Cost Breakdown by Contract and Site
An updated project team chart along with telephone numbers and addresses is also included.
Order work tasks fall under four basic categories: Interim Measures, RCRA Facility Investigation, Corrective Measures Study, and Corrective Measures Implementation. To meet the requirements of the Order, it is estimated that the majority of the work efforts will be part of the RCRA Facility Investigation and the Corrective Measures Implementation. As described in the first Quarterly Progress Report (reporting period: May 1, 1999 - July 30, 1999), Interim Measures, RCRA Facility Investigation, and Corrective Measures each account for approximately 30% of the Order tasks. The remaining 10% consist of the Corrective Measures Study.
Schedule
A master schedule detailing all of the required environmental activities specified in the Order, along with project activities under contract, was included in the Quarter 2 Progress Report.
Specific activities planned for the next quarter were described in the preceding sections.
Project Tasks and Costs Incurred to Date
Work at CSSA is currently being conducted under eight projects. The tasks included in each project and the percent complete are included in Table 1. As required by item IV.5.h of the Order, a statement reflecting the percentage of work accomplished thus far within the fiscal year and the percentages of funds expended to date will be reported in the progress report for Quarter 3 and every third progress report thereafter. A fiscal update, through Quarter 6, is included as Attachment 4.
Project Number |
Description of Task |
Relation to Order |
Percent Complete |
DO23 |
Project Management |
RFI |
100% |
Plan Addenda |
RFI |
100% |
|
Meetings |
RFI |
79% |
|
Sampling/Analysis |
RFI |
84% |
|
Well Upgrades |
RFI |
96% |
|
Well Installations |
RFI |
6% |
|
Hazardous Waste Management |
RFI |
96% |
|
RL17 |
RFI Scoping |
RFI |
100% |
Site Characterization |
RFI |
60% |
|
Treatability Investigations |
RFI |
95% |
|
Sampling and Analysis |
RFI |
90% |
|
Site Work and Utilities |
RFI |
100% |
|
Meeting Minutes Preparation |
RFI |
90% |
|
Presentation Materials |
RFI |
95% |
|
Letter Report Preparation |
RFI |
100% |
|
Project Management |
RFI |
100% |
|
Integrated Waste Management/Spill Plan |
NA |
100% |
|
Program Management |
RFI |
100% |
|
RL33 |
Project Management |
RFI |
99% |
Meetings |
RFI |
75% |
|
Project Plans |
RFI |
100% |
|
GIS |
RFI |
100% |
|
Site Investigations and UXO Clearance |
RFI |
89% |
|
B-20 Treatability Studies |
RFI |
97% |
|
IDW Management |
RFI |
0% |
|
Program Management |
RFI |
90% |
|
RL53 |
Project Management |
RFI |
98% |
Site Characterizations |
RFI |
65% |
|
Groundwater Wells |
RFI |
100% |
|
Sampling and Analysis |
RFI |
69% |
|
GIS |
RFI |
98% |
|
Project Plans |
RFI |
100% |
|
Meetings |
RFI |
55% |
|
Background Evaluation |
RFI |
80% |
|
Program Management |
RFI |
85% |
|
RL74 |
Project Management |
IM/RFI |
75% |
Meetings |
IM/RFI |
67% |
|
Groundwater Monitoring |
IM |
90% |
|
Pump Installation |
RFI |
0% |
|
SVE Operations & Maintenance |
RFI |
98% |
|
Plans |
RFI |
100% |
|
Current Conditions Report |
RFI |
100% |
|
O-1 Interim Measures |
IM |
100% |
|
H Order Support |
IM/RFI |
53% |
|
Building 40 Sampling |
RFI |
10% |
|
GIS and Web Site |
IM/RFI |
81% |
|
IDW Management |
RFI |
0% |
|
Groundwater Modeling |
RFI |
4% |
|
Encyclopedia Updates |
RFI |
100% |
|
Laboratory Audit |
IM/RFI |
100% |
|
Offsite Well Sampling |
IM |
100% |
|
Additional Rounds of Groundwater Monitoring |
IM/RFI |
15% |
|
Program Management |
RFI |
65% |
RL83 |
Project Management |
IM/RFI |
40% |
Meetings |
IM/RFI |
33% |
|
Well Research and Mapping |
RFI |
85% |
|
Hydrogeologic Conceptual Model |
RFI |
7% |
|
B-3 SVE Operations & Maintenance |
RFI |
23% |
|
Risk Assessment Conceptual Site Model |
RFI |
80% |
|
Cluster Well Installations |
RFI |
5% |
|
Quarterly Progress Reports |
IM/RFI |
60% |
|
SWMU and AOC Investigations |
RFI |
44% |
|
Soil Pile Disposition Assessment |
IM |
16% |
|
Encyclopedia Updates |
IM/RFI |
50% |
|
Title V Non-applicability Demonstration |
NA |
90% |
|
SPCC Plan Update |
NA |
53% |
|
TPDES Permit Update |
NA |
95% |
|
Laboratory Audit |
IM/RFI |
80% |
|
GIS Enhancements and Database Updates |
IM/RFI |
39% |
|
Groundwater Monitoring |
IM/RFI |
1% |
|
Community Relations Plan |
RFI |
100% |
|
DO5068 |
DO Management and Meetings |
IM/RFI |
42% |
Geophysics and Drilling |
RFI |
40% |
|
Surface Sampling |
RFI |
100% |
|
Soil Gas Survey |
RFI |
100% |
|
AOC 50 Interim Measures |
IM/RFI |
10% |
|
Workplans and Reporting |
RFI |
33% |
|
DO5084 |
DO Management and Meetings |
IM/RFI |
4% |
AOC 65 Phase II RFI |
RFI |
0% |
|
Soil Gas Surveys |
RFI |
0% |
|
AOC 67 Phase II RFI |
RFI |
0% |
|
On-Site Groundwater Monitoring |
IM/RFI |
0% |
|
Off-Site Groundwater Monitoring |
IM/RFI |
0% |
|
PIMS Study |
IM |
0% |
|
LAN Support |
NA |
0% |
|
Drought Contingency Plan |
NA |
0% |
|
Community Relations Plan Update |
RFI |
0% |
|
Lab Audit |
IM/RFI |
0% |
|
Aerial Photography |
NA |
0% |
|
Quarterly Reports |
IM/RFI |
0% |
Project Contacts
Contact information for key personnel involved with the CSSA projects are included in the table below.
Name |
Organization/ Role |
Street Address |
City, State, Zip |
Phone No. |
Fax No. |
Batschelet, Bill |
AFCEE/ERC |
|
|
|
|
Beal, Christopher |
CSSA/WPI |
c/o Environmental Office |
Boerne, TX 78015 |
(210) 698-5208 |
(210) 295-7386 |
Brown, Ed |
AFCEE/ERC |
3207 North Road |
Brooks AFB, TX 78235 |
(210) 536-5665 |
(210) 536-9026 |
Burdey, Julie |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6062 |
(512) 719-6099 |
Chang, Tammy |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6092 |
(512) 719-6099 |
Coulter, Kirk |
TNRCC |
P.O. Box 13087, MC 127 |
Austin, TX 78711-3087 |
(512) 239-2572 |
(512) 239-2346 |
Decker, Jon |
Parsons ES |
400 Woods Mill Rd. South, #330 |
Chesterfield, MO 63017 |
(314) 576-7330 |
(314) 576-0852 |
DuPiest, Teri |
Informatics Team |
|
|
(210) 536-5274 |
|
Fernando, Joe |
Informatics Team |
|
|
(210) 804-4332 |
|
Ghazizadeh, Michael |
WPI |
|
|
|
|
Gordon, Shavonne |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6011 |
(512) 719-6099 |
Hall, Cindy |
AETC Contracting Officer |
2021 First Street West |
Randolph AFB, TX 78150-4302 |
(210) 652-7885 |
(210) 652-2304 |
Hefner, Rene |
AFCEE/ERC |
3207 North Road |
Brooks AFB, TX 78235 |
(210) 536-4763 |
(210) 536-9026 |
Hewins, Stan |
WPI/A&M |
|
|
|
|
Hinchee, Robert |
Parsons ES |
406 E S. Jordan Pkwy, Suite 300 |
Salt Lake City, UT 84095 |
(801) 572-5999 |
(801) 572-9069 |
Howard, Brian |
Parsons ES |
3207 North Road |
Brooks AFB, TX 78235-5363 |
(210) 536-4755 |
(210) 536-5989 |
Kreke, Nancy |
AMC Contracting Officer |
|
|
|
|
Lyssy, Greg |
U.S. EPA |
1445 Ross Avenue (6SF-LT) |
Dallas, TX 75202-2733 |
(214) 665-8317 |
(214) 665-6660 |
McColloch, Craig |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6018 |
(512) 719-6099 |
Martinez, Maria |
U.S. EPA |
1445 Ross Avenue |
Dallas, TX 75202-2733 |
(214) 665-2230 |
|
Montemayor, Carlos |
AFCEE Contracting Specialist |
|
|
|
|
Mullen, Jo Jean |
AFCEE/ERD |
3207 North Road |
Brooks AFB, TX 78235 |
(210) 536-5940 |
(210) 536-9026 |
Murphy, Brian |
CSSA |
Environmental Office |
Boerne, TX 78015 |
(210) 698-5208 |
(210) 295-7386 |
Pearson, Scott |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6087 |
(512) 719-6099 |
Peten, Rachey |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6041 |
(512) 719-6099 |
Power, Abigail |
TNRCC |
140 Heimer Road, Suite 360 |
San Antonio, TX 78232-5042 |
(210) 403-4064 |
(210) 545-4329 |
Rembish, Steve |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6067 |
(512) 719-6099 |
Roberts, Susan |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6051 |
(512) 719-6099 |
Rossello, Steve |
Parsons ES |
290 Elwood Davis Rd, Suite 312 |
Liverpool, NY 13088 |
(315) 451-9560 |
(315) 451-9570 |
Rice, Ken |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6050 |
(512) 719-6099 |
Schrader, Steve |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6048 |
(512) 719-6099 |
Schoellman, Audrey |
AFCEE Contracting Officer |
|
|
|
|
Silva, Michele |
CSSA |
Environmental Office |
Boerne, TX 78015-4800 |
(210) 698-5208 |
(210) 295-7386 |
St. Clair, Tony |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6821 |
(512) 719-6099 |
Stine, Nancy |
AMC CONF/LGCFB |
507 Symington Dr, Rm W202 |
Scott AFB, IL 62225 |
|
|
Vail, Christina |
Parsons ES |
901 NE Loop 410, Suite 512 |
San Antonio, TX 78209 |
(210) 828-4900 |
(210) 828-9440 |
Vanderglas, Brian |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6059 |
(512) 719-6099 |
Wright, Judith |
UFA Ventures |
Two Camino Felix |
Santa Fe, NM 87501 |
(505) 455-1786 |
(505) 455-1788 |
Yu, John |
Parsons ES |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512) 719-6057 |
(512) 719-6099 |
Other
An on-site GIS presentation was made to CSSA and AFCEE on August 17, 2000. The presentation included a demonstration to the CSSA Commander and the facility engineering department. The presentation illustrated the concepts of utilizing GIS in the work place, and the applications already available through the infrastructure portion of the CSSA database. The environmental portion of the database was discussed with CSSA and AFCEE environmental staff. Issues regarding the compatibility between the TSSDS and ERPIMS data structures were identified and discussed. A demonstration of the data entry system was also provided. In addition, QA/QC procedures for both field sampling and data entry were discussed. The frequency at which duplicates and MS/MSD samples are submitted were reviewed, and it is was agreed that the program will continue under the same procedures.
Technical Interchange Meeting (TIM) #4 for RL74 was held at CSSA on September 5, 2000. Those in attendance included representatives from CSSA, AFCEE, WPI, and Parsons ES. In that meeting, an overall project status update for each currently funded project at CSSA was given. Parsons also provided an update regarding those IM activities currently being performed at SWMU B-10, and the estimated costs and actions necessary to complete the excavation activities based upon the changing field conditions. Reporting format and content for the Soil Pile Disposition Assessment Report and the O-1 IM/Closure Report were discussed.
On October 5, 2000 Parsons ES installed the CSSA GIS database, spatial (map) files, and a customized ESRI ArcView project for decision support at AFCEE. The visit included the uploading and testing of the GIS to the AFCEE SQL Server, as well as instruction in implementing the Graphical User Interface (GUI) for the retrieval and display of environmental sampling and analysis data from the GIS database.
During Quarter 6, CSSA and AFCEE finalized the Scope of Work for a new AETC RFI delivery order (DO 5084). New tasks included in this delivery order will include Phase II RFIs at AOCs 65 and 67, as well as a soil gas survey in the southwest quadrant of CSSA. Also included in this delivery order will be four rounds of onsite monitoring and six rounds of monitoring at 20 offsite locations, and a Drought Contingency Plan. The new delivery order will also fund the continuation of the TIMs, Community Relations Plan updates and fact sheets, and Quarterly Progress Reporting. The kick-off meeting for this delivery order was held at CSSA on October 3, 2000.
Susan Roberts has been identified as the Parsons ES project liaison for all CSSA work.