6th Quarter - Final Quarterly Progress Report

August 1, 2000 - October 31, 2000

Table of Contents

This quarterly progress report for CSSA, Texas, U.S. EPA Identification Number TX2210020739, is submitted in accordance with the Administrative Order on Consent (Order) issued to CSSA on May 5, 1999 pursuant to §3008(h) of the Solid Waste Disposal Act, as amended by RCRA, and further amended by the Hazardous and Solid Waste Amendments of 1984, 42 U.S.C. §6928(h). This report encompasses the fifth progress report period for the project and includes progress on the project from August 1, 2000 through October 31, 2000 (Quarter 6). Subsequent progress reports will continue to be submitted on a quarterly basis.

This report details work completed on tasks associated with four project phases outlined in the order. Phase names and task names listed below are taken directly from the Order. For each active task, the information requested in the Order is provided in this report. If the task is not yet active, that is also noted.

Interim Measures

Task I - Interim/Stabilization Measures Work Plan

Task II - Interim/Stabilization Measures Implementation

Task III - Reports

RCRA Facility Investigation

Task I - Preliminary Report: Description of Current Conditions

Task II - RFI Workplan

Task III - Facility Investigation

Task IV - Human Health and Ecological Risk Assessment

Task V - Investigation Analysis

Task VI - Treatability Studies

Task VII - Progress Reports

Corrective Measures Study

Task VIII - Identification and development of Corrective Action Alternatives

Task IX - Evaluation of Corrective Measures Alternatives

Task X - Reports

Corrective Measures Implementation

Task XI - Corrective Measure Implementation Program

Task XII - Corrective Measure Design

Task XIII - Corrective Measure Construction

Task XIV - Reports

Attachment 1 - Fiscal Report through September 2000

Table 1 - Budget Summary

Table 2 - Cost Breakdown by Contract and Site

An updated project team chart along with telephone numbers and addresses is also included.

Order work tasks fall under four basic categories: Interim Measures, RCRA Facility Investigation, Corrective Measures Study, and Corrective Measures Implementation. To meet the requirements of the Order, it is estimated that the majority of the work efforts will be part of the RCRA Facility Investigation and the Corrective Measures Implementation. As described in the first Quarterly Progress Report (reporting period: May 1, 1999 - July 30, 1999), Interim Measures, RCRA Facility Investigation, and Corrective Measures each account for approximately 30% of the Order tasks. The remaining 10% consist of the Corrective Measures Study.

Schedule

A master schedule detailing all of the required environmental activities specified in the Order, along with project activities under contract, was included in the Quarter 2 Progress Report.

Specific activities planned for the next quarter were described in the preceding sections. 

Project Tasks and Costs Incurred to Date

Work at CSSA is currently being conducted under eight projects. The tasks included in each project and the percent complete are included in Table 1. As required by item IV.5.h of the Order, a statement reflecting the percentage of work accomplished thus far within the fiscal year and the percentages of funds expended to date will be reported in the progress report for Quarter 3 and every third progress report thereafter. A fiscal update, through Quarter 6, is included as Attachment 4.

Project Number

Description of Task

Relation to Order

Percent Complete

DO23

Project Management

RFI

100%

Plan Addenda

RFI

100%

Meetings

RFI

79%

Sampling/Analysis

RFI

84%

Well Upgrades

RFI

96%

Well Installations

RFI

6%

Hazardous Waste Management

RFI

96%

RL17

RFI Scoping

RFI

100%

Site Characterization

RFI

60%

Treatability Investigations

RFI

95%

Sampling and Analysis

RFI

90%

Site Work and Utilities

RFI

100%

Meeting Minutes Preparation

RFI

90%

Presentation Materials

RFI

95%

Letter Report Preparation

RFI

100%

Project Management

RFI

100%

Integrated Waste Management/Spill Plan

NA

100%

Program Management

RFI

100%

RL33

Project Management

RFI

99%

Meetings

RFI

75%

Project Plans

RFI

100%

GIS

RFI

100%

Site Investigations and UXO Clearance

RFI

89%

B-20 Treatability Studies

RFI

97%

IDW Management

RFI

0%

Program Management

RFI

90%

RL53

Project Management

RFI

98%

Site Characterizations

RFI

65%

Groundwater Wells

RFI

100%

Sampling and Analysis

RFI

69%

GIS

RFI

98%

Project Plans

RFI

100%

Meetings

RFI

55%

Background Evaluation

RFI

80%

Program Management

RFI

85%

RL74

Project Management

IM/RFI

75%

Meetings

IM/RFI

67%

Groundwater Monitoring

IM

90%

Pump Installation

RFI

0%

SVE Operations & Maintenance

RFI

98%

Plans

RFI

100%

Current Conditions Report

RFI

100%

O-1 Interim Measures

IM

100%

H Order Support

IM/RFI

53%

Building 40 Sampling

RFI

10%

GIS and Web Site

IM/RFI

81%

IDW Management

RFI

0%

Groundwater Modeling

RFI

4%

Encyclopedia Updates

RFI

100%

Laboratory Audit

IM/RFI

100%

Offsite Well Sampling

IM

100%

Additional Rounds of Groundwater Monitoring

IM/RFI

15%

Program Management

RFI

65%

RL83

Project Management

IM/RFI

40%

Meetings

IM/RFI

33%

Well Research and Mapping

RFI

85%

Hydrogeologic Conceptual Model

RFI

7%

B-3 SVE Operations & Maintenance

RFI

23%

Risk Assessment Conceptual Site Model

RFI

80%

Cluster Well Installations

RFI

5%

Quarterly Progress Reports

IM/RFI

60%

SWMU and AOC Investigations

RFI

44%

Soil Pile Disposition Assessment

IM

16%

Encyclopedia Updates

IM/RFI

50%

Title V Non-applicability Demonstration

NA

90%

SPCC Plan Update

NA

53%

TPDES Permit Update

NA

95%

Laboratory Audit

IM/RFI

80%

GIS Enhancements and Database Updates

IM/RFI

39%

Groundwater Monitoring

IM/RFI

1%

Community Relations Plan

RFI

100%

DO5068

DO Management and Meetings

IM/RFI

42%

Geophysics and Drilling

RFI

40%

Surface Sampling

RFI

100%

Soil Gas Survey

RFI

100%

AOC 50 Interim Measures

IM/RFI

10%

Workplans and Reporting

RFI

33%

DO5084

DO Management and Meetings

IM/RFI

4%

AOC 65 Phase II RFI

RFI

0%

Soil Gas Surveys

RFI

0%

AOC 67 Phase II RFI

RFI

0%

On-Site Groundwater Monitoring

IM/RFI

0%

Off-Site Groundwater Monitoring

IM/RFI

0%

PIMS Study

IM

0%

LAN Support

NA

0%

Drought Contingency Plan

NA

0%

Community Relations Plan Update

RFI

0%

Lab Audit

IM/RFI

0%

Aerial Photography

NA

0%

Quarterly Reports

IM/RFI

0%

Project Contacts

Contact information for key personnel involved with the CSSA projects are included in the table below.

Name

Organization/ Role

Street Address

City, State, Zip

Phone No.

Fax No.

Batschelet, Bill

AFCEE/ERC
Chemist

 

 

 

 

Beal, Christopher

CSSA/WPI
Geologist and Environmental Assistant

c/o Environmental Office
25800 Ralph Fair Road

Boerne, TX 78015

(210) 698-5208

(210) 295-7386

Brown, Ed

AFCEE/ERC
AFCEE Chemist

3207 North Road

Brooks AFB, TX 78235

(210) 536-5665

(210) 536-9026

Burdey, Julie

Parsons ES
Mgr RL33, RL74, RL83

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6062

(512) 719-6099

Chang, Tammy

Parsons ES
Senior Scientist

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6092

(512) 719-6099

Coulter, Kirk

TNRCC
Project Mgr.

P.O. Box 13087, MC 127

Austin, TX 78711-3087

(512) 239-2572

(512) 239-2346

Decker, Jon

Parsons ES
Program Mgr.

400 Woods Mill Rd. South, #330

Chesterfield, MO 63017

(314) 576-7330

(314) 576-0852

DuPiest, Teri

Informatics Team
Project Mgr.

 

 

(210) 536-5274

 

Fernando, Joe

Informatics Team
Chemist

 

 

(210) 804-4332

 

Ghazizadeh, Michael

WPI
Project Mgr.

 

 

 

 

Gordon, Shavonne

Parsons ES
Task Mgr. and Geologist

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6011

(512) 719-6099

Hall, Cindy

AETC Contracting Officer

2021 First Street West

Randolph AFB, TX 78150-4302

(210) 652-7885

(210) 652-2304

Hefner, Rene

AFCEE/ERC
Hydrogeologist

3207 North Road

Brooks AFB, TX 78235

(210) 536-4763

(210) 536-9026

Hewins, Stan

WPI/A&M
Risk Assessor

 

 

 

 

Hinchee, Robert

Parsons ES
Technical Mgr., Remediation

406 E S. Jordan Pkwy, Suite 300

Salt Lake City, UT 84095

(801) 572-5999

(801) 572-9069

Howard, Brian

Parsons ES
Toxicologist Risk Assessor

3207 North Road

Brooks AFB, TX 78235-5363

(210) 536-4755

(210) 536-5989

Kreke, Nancy

AMC Contracting Officer 

 

 

 

 

Lyssy, Greg

U.S. EPA
Project Mgr

1445 Ross Avenue (6SF-LT)

Dallas, TX 75202-2733

(214) 665-8317

(214) 665-6660

McColloch, Craig

Parsons ES

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6018

(512) 719-6099

Martinez, Maria

U.S. EPA
Risk assessor

1445 Ross Avenue

Dallas, TX 75202-2733

(214) 665-2230

 

Montemayor, Carlos

AFCEE Contracting Specialist

 

 

 

 

Mullen, Jo Jean

AFCEE/ERD
AFCEE Team Chief
AMC QAE, COR

3207 North Road

Brooks AFB, TX 78235

(210) 536-5940

(210) 536-9026

Murphy, Brian

CSSA

Environmental Office
25800 Ralph Fair Road

Boerne, TX 78015

(210) 698-5208
(210) 861-5217

(210) 295-7386

Pearson, Scott

Parsons ES
DO5068 Project Mgr

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6087

(512) 719-6099

Peten, Rachey

Parsons ES
Task Mgr

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6041

(512) 719-6099

Power, Abigail

TNRCC
Environmental Investigator

140 Heimer Road, Suite 360

San Antonio, TX 78232-5042

(210) 403-4064

(210) 545-4329

Rembish, Steve

Parsons ES
Risk assessor

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6067

(512) 719-6099

Roberts, Susan

Parsons ES
Client services mgr.
DO23, RL17 Project Mgr.

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6051

(512) 719-6099

Rossello, Steve

Parsons ES
Task Mgr
GW Modeling

290 Elwood Davis Rd, Suite 312

Liverpool, NY 13088

(315) 451-9560

(315) 451-9570

Rice, Ken

Parsons ES
RL53 Project Mgr

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6050

(512) 719-6099

Schrader, Steve

Parsons ES
Task Mgr
TPDES Permit

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6048

(512) 719-6099

Schoellman, Audrey

AFCEE Contracting Officer

 

 

 

 

Silva, Michele

CSSA
Environmental Assistant

Environmental Office
25800 Ralph Fair Road

Boerne, TX 78015-4800

(210) 698-5208

(210) 295-7386

St. Clair, Tony

Parsons ES
Task Mgr
Air Permits

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6821

(512) 719-6099

Stine, Nancy

AMC CONF/LGCFB

507 Symington Dr, Rm W202

Scott AFB, IL 62225

 

 

Vail, Christina

Parsons ES
Task Mgr
SPCC Plan

901 NE Loop 410, Suite 512

San Antonio, TX 78209

(210) 828-4900

(210) 828-9440

Vanderglas, Brian

Parsons ES
Task Mgr
SVE O&M

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6059

(512) 719-6099

Wright, Judith

UFA Ventures

Two Camino Felix

Santa Fe, NM 87501

(505) 455-1786

(505) 455-1788

Yu, John

Parsons ES
Technical Director

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512) 719-6057

(512) 719-6099

Other

An on-site GIS presentation was made to CSSA and AFCEE on August 17, 2000. The presentation included a demonstration to the CSSA Commander and the facility engineering department. The presentation illustrated the concepts of utilizing GIS in the work place, and the applications already available through the infrastructure portion of the CSSA database. The environmental portion of the database was discussed with CSSA and AFCEE environmental staff. Issues regarding the compatibility between the TSSDS and ERPIMS data structures were identified and discussed. A demonstration of the data entry system was also provided. In addition, QA/QC procedures for both field sampling and data entry were discussed. The frequency at which duplicates and MS/MSD samples are submitted were reviewed, and it is was agreed that the program will continue under the same procedures.

Technical Interchange Meeting (TIM) #4 for RL74 was held at CSSA on September 5, 2000. Those in attendance included representatives from CSSA, AFCEE, WPI, and Parsons ES. In that meeting, an overall project status update for each currently funded project at CSSA was given. Parsons also provided an update regarding those IM activities currently being performed at SWMU B-10, and the estimated costs and actions necessary to complete the excavation activities based upon the changing field conditions. Reporting format and content for the Soil Pile Disposition Assessment Report and the O-1 IM/Closure Report were discussed.

On October 5, 2000 Parsons ES installed the CSSA GIS database, spatial (map) files, and a customized ESRI ArcView project for decision support at AFCEE. The visit included the uploading and testing of the GIS to the AFCEE SQL Server, as well as instruction in implementing the Graphical User Interface (GUI) for the retrieval and display of environmental sampling and analysis data from the GIS database.

During Quarter 6, CSSA and AFCEE finalized the Scope of Work for a new AETC RFI delivery order (DO 5084). New tasks included in this delivery order will include Phase II RFIs at AOCs 65 and 67, as well as a soil gas survey in the southwest quadrant of CSSA. Also included in this delivery order will be four rounds of onsite monitoring and six rounds of monitoring at 20 offsite locations, and a Drought Contingency Plan. The new delivery order will also fund the continuation of the TIMs, Community Relations Plan updates and fact sheets, and Quarterly Progress Reporting. The kick-off meeting for this delivery order was held at CSSA on October 3, 2000.

Susan Roberts has been identified as the Parsons ES project liaison for all CSSA work.