3rd and 4th Quarters, November 1, 1999 - January 31, 2000/February 1 - April 30, 2000

Final Quarterly Progress Report

Table of Contents

This fourth quarterly progress report for Camp Stanley Storage Activity (CSSA), Texas, U.S. Environmental Protection Agency (EPA) Identification Number TX2210020739, is submitted in accordance with the Administrative Order on Consent (Order) issued to CSSA on May 5, 1999 pursuant to §3008(h) of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act (RCRA), and further amended by the Hazardous and Solid Waste Amendments of 1984, 42 United States Code (U.S.C.) §6928(h). This report encompasses the third and fourth progress report periods for the project. Although this is the fourth quarterly report, it includes progress on the project from November 1, 1999 through January 31, 2000 (Quarter 3) and from February 1, 2000 through April 30, 2000 (Quarter 4). Subsequent progress reports will continue to be submitted on a quarterly basis.

This report details work completed on tasks associated with four project phases outlined in the Order. Phase names and task names listed below are taken directly from the Order. For each active task, the information requested in the Order is provided in this report. If the task is not yet active, that is also noted.

Interim Measures

Task I - Interim/Stabilization Measures Work Plan

Task II - Interim/Stabilization Measures Implementation

Task III - Reports

RCRA Facility Investigation

Task I - Preliminary Report: Description of Current Conditions

Task II - RFI Work Plan

Task III - Facility Investigation

Task IV - Human Health and Ecological Risk Assessment

Task V - Investigation Analysis

Task VI - Treatability Studies

Task VII - Progress Reports

Corrective Measures Study

Task VIII - Identification and Development of Corrective Action Alternatives

Task IX - Evaluation of Corrective Measures Alternatives

Task X - Reports

Corrective Measures Implementation

Task XI - Corrective Measure Implementation Program Plan

Task XII - Corrective Measure Design

Task XIII - Corrective Measure Construction

Task XIV - Reports

Attachment 1

An updated Project Team Chart along with telephone numbers and addresses is also included.

Order work tasks include four basic categories: Interim Measures, RCRA Facility Investigation, Corrective Measures Study, and Corrective Measures Implementation. To meet the requirements of the Order, it is estimated that the majority of the work efforts will be part of the RCRA Facility Investigation and the Corrective Measures Implementation. As described in the first Quarterly Progress Report (reporting period: May 1, 1999 – July 30, 1999), Interim Measures, RCRA Facility Investigation, and Corrective Measures Implementation each account for approximately 30% of the Order tasks. The remaining 10% consists of the Corrective Measures Study (Attachment 1).

Schedule

A master schedule detailing all of the required environmental activities specified in the Order, along with project activities under contract, was included in the Quarter 2 Progress Report.

Specific activities planned for the next quarter were described in the preceding sections.

Project Tasks and Costs Incurred to Date

Work at CSSA is currently being conducted under seven projects. The tasks included in each project and the percent complete are included in the table below. As required by item VI.5.h of the order, a statement reflecting the percentage of work accomplished thus far within the fiscal year and the percentage of funds expended to date will be reported in the progress report for Quarter 3 and every third progress report thereafter. A fiscal update, through Quarter 3, is included as Attachment 6.

Project Number

Description of Task

Relation to Order

Percent Complete

DO23

Project Management

RFI

95%

Plan Addenda

RFI

100%

Meetings

RFI

70%

Sampling/Analysis

RFI

90%

Well Upgrades

RFI

94%

Well Installations

RFI

5%

Hazardous Waste Management

RFI

75%

RL17

RFI Scoping

RFI

100%

Site Characterization

RFI

60%

Treatability Investigations

RFI

95%

Sampling and Analysis

RFI

90%

Site Work and Utilities

RFI

100%

Meeting Minutes Preparation

RFI

90%

Presentation Materials

RFI

95%

Letter Report Preparation

RFI

100%

Project Management

RFI

100%

Integrated Waste Management/Spill Plan

NA

100%

Program Management

RFI

100%

RL33

Project Management

RFI

99%

Meetings

RFI

60%

Project Plans

RFI

100%

GIS

RFI

100%

Site Investigations and UXO Clearance

RFI

84%

B-20 Treatability Studies

RFI

95%

IDW Management

RFI

0%

Program Management

RFI

80%

RL53

Project Management

RFI

91%

Site Characterizations

RFI

45%

Groundwater Wells

RFI

0%

Sampling and Analysis

RFI

12%

GIS

RFI

96%

Project Plans

RFI

100%

Meetings

RFI

51%

Background Evaluation

RFI

77%

Program Management

RFI

75%

RL74

Project Management

IM/RFI

53%

Meetings

IM/RFI

65%

Groundwater Monitoring

IM

36%

Pump Installation

RFI

0%

SVE Operations & Maintenance

RFI

36%

Plans

RFI

100%

Current Conditions Report

RFI

100%

O-1 Interim Measures

IM

50%

H Order Support

IM/RFI

65%

Building 40 Sampling

RFI

10%

GIS and Web Site

IM/RFI

73%

IDW Management

RFI

0%

Groundwater Modeling

RFI

10%

Encyclopedia Updates

RFI

100%

Laboratory Audit

IM/RFI

100%

Offsite Well Sampling

IM

98%

Additional Rounds of Groundwater Monitoring

IM/RFI

1%

Program Management

RFI

50%

RL83

Project Management

IM/RFI

28%

Meetings

IM/RFI

20%

Well Research and Mapping

RFI

70%

Hydrogeologic Conceptual Model

RFI

7%

B-3 SVE Operations & Maintenance

RFI

14%

Risk Assessment Conceptual Site Model

RFI

42%

Cluster Well Installations

RFI

8%

Quarterly Progress Reports

IM/RFI

45%

SWMU and AOC Investigations

RFI

40%

Soil Pile Disposition Assessment

IM

10%

Encyclopedia Updates

IM/RFI

30%

Title V Non-applicability Demonstration

NA

50%

SPCC Plan Update

NA

75%

TPDES Permit Update

NA

90%

Laboratory Audit

IM/RFI

75%

GIS Enhancements and Database Updates

IM/RFI

30%

Groundwater Monitoring

IM/RFI

1%

Community Relations Plan

RFI

96%

Program Management

IM/RFI

25%

DO 5068

DO Management and Meetings

IM/RFI

29%

Geophysics and Drilling

RFI

40%

Surface Sampling

RFI

100%

Soil Gas Surveys

RFI

100%

AOC 50 Interim Measures

IM/RFI

10%

Workplans and Reporting

RFI

30%

Project Team

The project team consists of personnel from U.S. EPA, TNRCC, CSSA, AFCEE, WPI, Informatics Team, AMC, AETC, HSC contracting, Parsons ES, and subcontractors. Contact information is provided in the following table.

Name

Organization/ Role

Street Address

City, State, Zip

Phone No.

Fax No.

Batschelet, Bill

AFCEE/ERC Chemist

 

 

 

 

Beal, Christopher

CSSA/WPI, Geologist and Environmental Assistant

c/o Environmental Office, 25800 Ralph Fair Road

Boerne, TX 78015-4800

(210)698-5208

(210)295-7386

Brown, Ed

AFCEE/ERC AFCEE chemist

3207 North Road

Brooks AFB, TX 78235-5363

(210)536-5665

(210)536-9026

Burdey, Julie

Parsons ES Project Mgr. RL74, RL83

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6062

(512)719-6099

Chang, Tammy

Parsons ES Senior Scientist

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6092

(512)719-6099

Coulter, Kirk

TNRCC Project Mgr.

P.O. Box 13087, MC 127

Austin, TX 78711-3087

(5120239-2572

(512)239-2346

Decker, Jon

Parsons ES Program Mgr. for AMC

400 Woods Mill Rd. South, #330

Chesterfield, MO 63017

(314)576-7330

(314)576-0852

DuPriest, Teri

Informatics Team Project Manager

 

 

(210)536-5274

 

Fernando, Joe

Informatics Team Chemist

 

 

(210)804-4332

 

Ghazizadeh, Michael

WPI Project Manager

 

 

 

 

Gordon, Shavonne

Parsons ES Task Mgr. Geologist

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6011

(512)719-6099

Hall, Cindy

AETC Contracting Officer

2021 First Street West

Randolph AFB, TX 78150-4302

(210)652-7885

(210)652-2304

Hefner, Rene

AFCEE/ERC Hydrogeologist

3207 North Road, Bldg. 532

Brooks AFB, TX 78235-5363

(210)536-4763

(210)536-9026

Hewins, Stan

WPI/A&M Risk Assessment

 

 

 

 

Hinchee, Robert

Parsons ES Technical Mgr., Remediation

406 E S. Jordan Pkwy, Suite 300

Salt Lake City, UT 84095

(801)572-5999

(801)572-9069

Howard, Brian

AFCEE/ERC Toxicologist Risk Assessor

3207 North Road

Brooks AFB, TX 78235-5363

(210) 536-4755

(210) 536-5989

Kreke, Nancy

AMC Contracting Officer

 

 

 

 

Lyssy, Greg

U.S. EPA Project Mgr.

1445 Ross Avenue (6SF-LT)

Dallas, TX 75202-2733

(214)665-8317

(214)665-6660

McColloch, Craig

Parsons ES Program Mgr. For AETC

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6018

(512)719-6099

Martinez, Maria

U.S. EPA Risk Assessor

1445 Ross Avenue

Dallas, TX 75202-2733

(214) 665-2230

 

Montemayor, Carlos

AFCEE Contracting Specialist

 

 

 

 

Mullen, Jo Jean

AFCEE/ERD AFCEE Team Chief AMC QAE, COR

3207 North Road

Brooks AFB, TX 78235-5363

(210)536-5940

(210)536-9026

Murphy, Brian

CSSA

Environmental Office 25800 Ralph Fair Road

Boerne, TX 78015-4800

(210)698-5208
(210)861-5217

(210)295-7386

Pearson, Scott

Parsons ES Project Mgr. For AETC

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6087

(512)719-6099

Peten, Rachey

Parsons ES Task Manager

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6041

(512)719-6099

Rembish, Steve

Parsons ES Risk Assessor

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6067

(512)719-6099

Rice, Ken

Parsons ES Project Mgr. For RL53

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6050

(512)719-6099

Roberts, Susan

Client Services Mgr. Parsons ES Project Mgr. DO23, RL17

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6051

(512)719-6099

Rossello, Steve

Parsons ES Task Mgr. GW Modeling

290 Elwood Davis Rd, Suite 312

Liverpool, NY 13088

(315)451-9560

(315)451-9570

St. Clair, Tony

Parsons ES Task Mgr., Air Permits

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6821

(512)719-6099

Schoellman, Audrey

AFCEE Contracting Officer

Schrader, Steve

Parsons ES Task Mgr., TPDES Permits

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6048

(512)719-6099

Silva, Michele

CSSA Environmental Assistant

Environmental Office, 25800 Ralph Fair Road

Boerne, TX 78015-4800

(210) 698-5208

(210)295-7386

Stapleton, Mark

Informatics Team Engineer

       

Stine, Nancy

AMC CONF/LGCFB Contract Officer

507 Symington Dr, Rm W202

Scott AFB, IL 62225

(618) 256-9956

(618) 256-3091

Vail, Christina

Parsons ES Task Mgr., SPCC Plan Updates

901 NE Loop 410, Suite 512

San Antonio, TX 78209

(210)828-4900

(210)828-9440

Vanderglas, Brian

Parsons ES Task Mgr., SVE O&M

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6059

(512)719-6099

Wright, Judith

UFA Ventures

Two Camino Felix

Santa Fe, NM 87501

(505)455-1786

(505)455-1788

Yu, John

Parsons ES Technical Director

8000 Centre Park Dr., Suite 200

Austin, TX 78754

(512)719-6057

(512)719-6099