3rd and 4th
Quarters, November 1, 1999 - January 31, 2000/February 1 - April 30, 2000Final Quarterly Progress Report
Table of Contents
This fourth quarterly progress report for Camp Stanley Storage Activity (CSSA), Texas, U.S. Environmental Protection Agency (EPA) Identification Number TX2210020739, is submitted in accordance with the Administrative Order on Consent (Order) issued to CSSA on May 5, 1999 pursuant to §3008(h) of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act (RCRA), and further amended by the Hazardous and Solid Waste Amendments of 1984, 42 United States Code (U.S.C.) §6928(h). This report encompasses the third and fourth progress report periods for the project. Although this is the fourth quarterly report, it includes progress on the project from November 1, 1999 through January 31, 2000 (Quarter 3) and from February 1, 2000 through April 30, 2000 (Quarter 4). Subsequent progress reports will continue to be submitted on a quarterly basis.
This report details work completed on tasks associated with four project phases outlined in the Order. Phase names and task names listed below are taken directly from the Order. For each active task, the information requested in the Order is provided in this report. If the task is not yet active, that is also noted.
Task I - Interim/Stabilization Measures Work Plan
Task II - Interim/Stabilization Measures Implementation
Task I - Preliminary Report: Description of Current Conditions
Task III - Facility Investigation
Task IV - Human Health and Ecological Risk Assessment
Task V - Investigation Analysis
Task VI - Treatability Studies
Task VIII - Identification and Development of Corrective Action Alternatives
Task IX - Evaluation of Corrective Measures Alternatives
Corrective Measures Implementation
Task XI - Corrective Measure Implementation Program Plan
Task XII - Corrective Measure Design
Task XIII - Corrective Measure Construction
Attachment 1
An updated Project Team Chart along with telephone numbers and addresses is also included.
Order work tasks include four basic categories: Interim Measures, RCRA Facility Investigation, Corrective Measures Study, and Corrective Measures Implementation. To meet the requirements of the Order, it is estimated that the majority of the work efforts will be part of the RCRA Facility Investigation and the Corrective Measures Implementation. As described in the first Quarterly Progress Report (reporting period: May 1, 1999 – July 30, 1999), Interim Measures, RCRA Facility Investigation, and Corrective Measures Implementation each account for approximately 30% of the Order tasks. The remaining 10% consists of the Corrective Measures Study (Attachment 1).
Schedule
A master schedule detailing all of the required environmental activities specified in the Order, along with project activities under contract, was included in the Quarter 2 Progress Report.
Specific activities planned for the next quarter were described in the preceding sections.
Project Tasks and Costs Incurred to Date
Work at CSSA is currently being conducted under seven projects. The tasks included in each project and the percent complete are included in the table below. As required by item VI.5.h of the order, a statement reflecting the percentage of work accomplished thus far within the fiscal year and the percentage of funds expended to date will be reported in the progress report for Quarter 3 and every third progress report thereafter. A fiscal update, through Quarter 3, is included as Attachment 6.
Project Number |
Description of Task |
Relation to Order |
Percent Complete |
DO23 |
Project Management |
RFI |
95% |
Plan Addenda |
RFI |
100% |
|
Meetings |
RFI |
70% |
|
Sampling/Analysis |
RFI |
90% |
|
Well Upgrades |
RFI |
94% |
|
Well Installations |
RFI |
5% |
|
Hazardous Waste Management |
RFI |
75% |
|
RL17 |
RFI Scoping |
RFI |
100% |
Site Characterization |
RFI |
60% |
|
Treatability Investigations |
RFI |
95% |
|
Sampling and Analysis |
RFI |
90% |
|
Site Work and Utilities |
RFI |
100% |
|
Meeting Minutes Preparation |
RFI |
90% |
|
Presentation Materials |
RFI |
95% |
|
Letter Report Preparation |
RFI |
100% |
|
Project Management |
RFI |
100% |
|
Integrated Waste Management/Spill Plan |
NA |
100% |
|
Program Management |
RFI |
100% |
|
RL33 |
Project Management |
RFI |
99% |
Meetings |
RFI |
60% |
|
Project Plans |
RFI |
100% |
|
GIS |
RFI |
100% |
|
Site Investigations and UXO Clearance |
RFI |
84% |
|
B-20 Treatability Studies |
RFI |
95% |
|
IDW Management |
RFI |
0% |
|
Program Management |
RFI |
80% |
|
RL53 |
Project Management |
RFI |
91% |
Site Characterizations |
RFI |
45% |
|
Groundwater Wells |
RFI |
0% |
|
Sampling and Analysis |
RFI |
12% |
|
GIS |
RFI |
96% |
|
Project Plans |
RFI |
100% |
|
Meetings |
RFI |
51% |
|
Background Evaluation |
RFI |
77% |
|
Program Management |
RFI |
75% |
|
RL74 |
Project Management |
IM/RFI |
53% |
Meetings |
IM/RFI |
65% |
|
Groundwater Monitoring |
IM |
36% |
|
Pump Installation |
RFI |
0% |
|
SVE Operations & Maintenance |
RFI |
36% |
|
Plans |
RFI |
100% |
|
Current Conditions Report |
RFI |
100% |
|
O-1 Interim Measures |
IM |
50% |
|
H Order Support |
IM/RFI |
65% |
|
Building 40 Sampling |
RFI |
10% |
|
GIS and Web Site |
IM/RFI |
73% |
|
IDW Management |
RFI |
0% |
|
Groundwater Modeling |
RFI |
10% |
|
Encyclopedia Updates |
RFI |
100% |
|
Laboratory Audit |
IM/RFI |
100% |
|
Offsite Well Sampling |
IM |
98% |
|
Additional Rounds of Groundwater Monitoring |
IM/RFI |
1% |
|
Program Management |
RFI |
50% |
RL83 |
Project Management |
IM/RFI |
28% |
Meetings |
IM/RFI |
20% |
|
Well Research and Mapping |
RFI |
70% |
|
Hydrogeologic Conceptual Model |
RFI |
7% |
|
B-3 SVE Operations & Maintenance |
RFI |
14% |
|
Risk Assessment Conceptual Site Model |
RFI |
42% |
|
Cluster Well Installations |
RFI |
8% |
|
Quarterly Progress Reports |
IM/RFI |
45% |
|
SWMU and AOC Investigations |
RFI |
40% |
|
Soil Pile Disposition Assessment |
IM |
10% |
|
Encyclopedia Updates |
IM/RFI |
30% |
|
Title V Non-applicability Demonstration |
NA |
50% |
|
SPCC Plan Update |
NA |
75% |
|
TPDES Permit Update |
NA |
90% |
|
Laboratory Audit |
IM/RFI |
75% |
|
GIS Enhancements and Database Updates |
IM/RFI |
30% |
|
Groundwater Monitoring |
IM/RFI |
1% |
|
Community Relations Plan |
RFI |
96% |
|
Program Management |
IM/RFI |
25% |
|
DO 5068 |
DO Management and Meetings |
IM/RFI |
29% |
Geophysics and Drilling |
RFI |
40% |
|
Surface Sampling |
RFI |
100% |
|
Soil Gas Surveys |
RFI |
100% |
|
AOC 50 Interim Measures |
IM/RFI |
10% |
|
Workplans and Reporting |
RFI |
30% |
The project team consists of personnel from U.S. EPA, TNRCC, CSSA, AFCEE, WPI, Informatics Team, AMC, AETC, HSC contracting, Parsons ES, and subcontractors. Contact information is provided in the following table.
Name |
Organization/ Role |
Street Address |
City, State, Zip |
Phone No. |
Fax No. |
Batschelet, Bill |
AFCEE/ERC Chemist |
|
|
|
|
Beal, Christopher |
CSSA/WPI, Geologist and Environmental Assistant |
c/o Environmental Office, 25800 Ralph Fair Road |
Boerne, TX 78015-4800 |
(210)698-5208 |
(210)295-7386 |
Brown, Ed |
AFCEE/ERC AFCEE chemist |
3207 North Road |
Brooks AFB, TX 78235-5363 |
(210)536-5665 |
(210)536-9026 |
Burdey, Julie |
Parsons ES Project Mgr. RL74, RL83 |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6062 |
(512)719-6099 |
Chang, Tammy |
Parsons ES Senior Scientist |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6092 |
(512)719-6099 |
Coulter, Kirk |
TNRCC Project Mgr. |
P.O. Box 13087, MC 127 |
Austin, TX 78711-3087 |
(5120239-2572 |
(512)239-2346 |
Decker, Jon |
Parsons ES Program Mgr. for AMC |
400 Woods Mill Rd. South, #330 |
Chesterfield, MO 63017 |
(314)576-7330 |
(314)576-0852 |
DuPriest, Teri |
Informatics Team Project Manager |
|
|
(210)536-5274 |
|
Fernando, Joe |
Informatics Team Chemist |
|
|
(210)804-4332 |
|
Ghazizadeh, Michael |
WPI Project Manager |
|
|
|
|
Gordon, Shavonne |
Parsons ES Task Mgr. Geologist |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6011 |
(512)719-6099 |
Hall, Cindy |
AETC Contracting Officer |
2021 First Street West |
Randolph AFB, TX 78150-4302 |
(210)652-7885 |
(210)652-2304 |
Hefner, Rene |
AFCEE/ERC Hydrogeologist |
3207 North Road, Bldg. 532 |
Brooks AFB, TX 78235-5363 |
(210)536-4763 |
(210)536-9026 |
Hewins, Stan |
WPI/A&M Risk Assessment |
|
|
|
|
Hinchee, Robert |
Parsons ES Technical Mgr., Remediation |
406 E S. Jordan Pkwy, Suite 300 |
Salt Lake City, UT 84095 |
(801)572-5999 |
(801)572-9069 |
Howard, Brian |
AFCEE/ERC Toxicologist Risk Assessor |
3207 North Road |
Brooks AFB, TX 78235-5363 |
(210) 536-4755 |
(210) 536-5989 |
Kreke, Nancy |
AMC Contracting Officer |
|
|
|
|
Lyssy, Greg |
U.S. EPA Project Mgr. |
1445 Ross Avenue (6SF-LT) |
Dallas, TX 75202-2733 |
(214)665-8317 |
(214)665-6660 |
McColloch, Craig |
Parsons ES Program Mgr. For AETC |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6018 |
(512)719-6099 |
Martinez, Maria |
U.S. EPA Risk Assessor |
1445 Ross Avenue |
Dallas, TX 75202-2733 |
(214) 665-2230 |
|
Montemayor, Carlos |
AFCEE Contracting Specialist |
|
|
|
|
Mullen, Jo Jean |
AFCEE/ERD AFCEE Team Chief AMC QAE, COR |
3207 North Road |
Brooks AFB, TX 78235-5363 |
(210)536-5940 |
(210)536-9026 |
Murphy, Brian |
CSSA |
Environmental Office 25800 Ralph Fair Road |
Boerne, TX 78015-4800 |
(210)698-5208 |
(210)295-7386 |
Pearson, Scott |
Parsons ES Project Mgr. For AETC |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6087 |
(512)719-6099 |
Peten, Rachey |
Parsons ES Task Manager |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6041 |
(512)719-6099 |
Rembish, Steve |
Parsons ES Risk Assessor |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6067 |
(512)719-6099 |
Rice, Ken |
Parsons ES Project Mgr. For RL53 |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6050 |
(512)719-6099 |
Roberts, Susan |
Client Services Mgr. Parsons ES Project Mgr. DO23, RL17 |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6051 |
(512)719-6099 |
Rossello, Steve |
Parsons ES Task Mgr. GW Modeling |
290 Elwood Davis Rd, Suite 312 |
Liverpool, NY 13088 |
(315)451-9560 |
(315)451-9570 |
St. Clair, Tony |
Parsons ES Task Mgr., Air Permits |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6821 |
(512)719-6099 |
Schoellman, Audrey |
AFCEE Contracting Officer |
||||
Schrader, Steve |
Parsons ES Task Mgr., TPDES Permits |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6048 |
(512)719-6099 |
Silva, Michele |
CSSA Environmental Assistant |
Environmental Office, 25800 Ralph Fair Road |
Boerne, TX 78015-4800 |
(210) 698-5208 |
(210)295-7386 |
Stapleton, Mark |
Informatics Team Engineer |
||||
Stine, Nancy |
AMC CONF/LGCFB Contract Officer |
507 Symington Dr, Rm W202 |
Scott AFB, IL 62225 |
(618) 256-9956 |
(618) 256-3091 |
Vail, Christina |
Parsons ES Task Mgr., SPCC Plan Updates |
901 NE Loop 410, Suite 512 |
San Antonio, TX 78209 |
(210)828-4900 |
(210)828-9440 |
Vanderglas, Brian |
Parsons ES Task Mgr., SVE O&M |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6059 |
(512)719-6099 |
Wright, Judith |
UFA Ventures |
Two Camino Felix |
Santa Fe, NM 87501 |
(505)455-1786 |
(505)455-1788 |
Yu, John |
Parsons ES Technical Director |
8000 Centre Park Dr., Suite 200 |
Austin, TX 78754 |
(512)719-6057 |
(512)719-6099 |