Quarterly Progress Report
November 1, 1999 – January 31, 2000 (3rd Quarter) and February 1, 2000 – April 30, 2000 (4th Quarter)

Corrective Measures Implementation

The purpose of the Corrective Measures Implementation (CMI) is to design, construct, operate, maintain, and monitor the performance of corrective measure(s) selected to protect human health and the environment. The CMI consists of a CMI Program Plan, Corrective Measure Design, Corrective Measure Construction, and Reports. The CMI is estimated to represent approximately 30% of the required actions at CSSA. The CMI includes implementation of the program plan (5% of CMI), corrective measure design (15%), corrective measure construction (70%), and reports (10%). The CMI has not yet been initiated.

Task XI: Corrective Measure Implementation Program Plan

This CMI Program Plan task includes preparation of a Program Management Plan and an update to the Community Relations Plan. The Program Management Plan will document the overall strategy for performing the design, construction, operation, maintenance, and monitoring of corrective measures. The Community Relations Plan will be updated to reflect knowledge of citizen concerns. In addition, a public notice and fact sheet will be distributed at the completion of the engineering design.

Completion of this task is not funded. This task makes up approximately 5% of the CMI phase. It was not active during Quarters 3 and 4, and no actions are anticipated during Quarter 5.

Task XII: Corrective Measure Design

This Corrective Measure Design task includes preparation of a report which will address requirements necessary to implement the selected corrective measures, as defined in the CMS. It will include design plans and specifications, an operation and maintenance plan, a cost estimate, project schedule, construction quality assurance objectives, health and safety plan, and design phases.

Completion of this task is not funded. This task makes up approximately 15% of the CMI phase. It was not active during Quarters 3 and 4, and no actions are anticipated during Quarter 5.

Task XIII: Corrective Measure Construction

This Corrective Measure Construction task includes preparation of a construction Quality Assurance Plan to ensure, with a reasonable degree of certainty, that a completed corrective measure meets or exceeds all design criteria, plans, and specifications. The plan will describe the responsibility and authority of all organizations involved in the construction, inspection activities, and sampling requirements. Upon completion of the plan, the corrective measures will be constructed and implemented according to the plan.

Completion of this task is not funded. This task makes up approximately 70% of the CMI phase. It was not active during Quarters 3 and 4, and no actions are anticipated during Quarter 5.

Task XIV: Reports

Reports associated with the CMI include progress reports, a CMI Program Plan, CM Design Report, Construction Quality Assurance Plan, and a final Corrective measure Implementation Report.

Completion of this task is not funded. This task makes up approximately 10% of the CMI phase. It was not active during Quarters 3 and 4, and no actions are anticipated during Quarter 5.