Minutes for TIM Meeting #8 - Contract No. AMC F11623-94-D0024, RL83

Parsons #736071.02000

Date:

May 1, 2003

Time:

8:30 A.M. - 5:00 P.M.

Place:

Parsons, Austin, Texas

Subject:

Financial updates on all active projects, status of remaining tasks

Attendees:

 

Attendee

Organization

Phone

Brian K. Murphy

CSSA ENV

(210) 698-5208

Julie Burdey

Parsons

(512) 719-6062

Gary Cobb

Parsons

(512) 719-6011

Kate Griffin

Parsons

(512) 719-6027

Kirk Lawson

Parsons

(512) 719-6009

Eric North

Parsons

(512) 719-6054

Scott Pearson

Parsons

(512) 719-6087

Garner Peterson

Parsons

(512) 719-6817

Ken Rice

Parsons

(512) 719-6050

Kimberly Riley

Parsons

(512) 719-6816

Brian Vanderglas

Parsons

(512) 719-6059

Minutes prepared by Julie Burdey, Parsons.

TIM #8 Meeting at Parsons

A summary of the action items reached in the May 1, 2003, meeting regarding the status of remaining tasks on all active projects is included below.  The meeting agenda is provided in Attachment 1.

RL17 Update:

The status of RL17 (Attachment 2) was discussed, including a financial update, the summary of the SWMU/AOC status review, the potential for additional sampling with available.  Results for recent additional sampling at SWMUs B-8, B-34, and Bldg 43 were discussed.  Action items resulting from the RL17 discussions were:

Action Item:   Due to unanticipated elevated concentrations of lead at SWMU B-8, CSSA requested that, for the upcoming SWMU Closure Project (TO0019), SWMU B-8 be replaced with AOCs 38 and 41. 

Action Item:    Parsons will conduct additional soil sampling and analysis using field test kits at SWMUs B-8 and possibly Building 43 to better define the extent of contamination. 

Action Item:   Parsons will research the possible use of Texas Railroad Commission rules for addressing lead contamination along the railroad tracks at SWMU B-34.

Action Item:   CSSA considers the B-3 SVE Test Report submitted in November 2001 to be the final version of the document; therefore, Parsons will clarify this in the May 2002 RL17 monthly progress report.

RL74 Update:

The status of RL74 (Attachment 3) was discussed and included a discussion of the financial status, the schedule for completion of tasks, the groundwater model linking task, Bldg 40 closure, and the upcoming new aerial photograph of CSSA.  Action items resulting from the RL74 discussions included:

Action Item:   Parsons will continue coordination with Terrapoint to arrange for a late May aerial photograph.

Action Item:   Parsons will wash floors in Building 40 and collect sample of rinsate water to verify that all waste residue has been removed.  Following analysis and validation, a closure report will be prepared.

Action Item:   Parsons will discuss the groundwater model task with Steve Rosello (Parsons modeling expert) and CSSA to determine the most cost-effective and efficient means to achieve CSSA’s goals (visual representations of the groundwater conceptual site model).

RL53 Update:

The status of RL53 (Attachment 4) was discussed and included the financial status and status SWMU B-10 draft closure report.  Additional waste removal and sampling has been completed, and the final closure report is currently being prepared.  After the final B-10 report has been submitted, the project will be complete.

Action Item:   Parsons will complete the final SWMU B-10 Closure Report.

RL83 Update:

RL83’s financial and project status (Attachment 5) was discussed, as well as the Soil Pile Disposition Assessment task and the Conceptual Site Model.  The outline of the CSM Report was discussed.  Action items resulting from the RL83 discussions included:

Action Item:   Parsons will prepare final Well Installation Report, pending AFCEE comments.  CSSA comments were received on April 26, 2003.

Action Item:   Parsons will prepare final Soil Pile Disposition Assessment report, pending CSSA and AFCEE comments.  Bench-scale treatability studies will then be conducted at SWMUs B-24 and B-28.  Recent B-8 results indicate that a treatability study may also be appropriate at this site.

Action Item:   Parsons will prepare final SWMU B-23A RFI Report, pending CSSA and AFCEE comments.

Action Item:   CSSA would like to conduct further SVE O&M at SWMU B-3 under this delivery order.  Parsons will discuss possible modification to project to conduct this work at SWMU B-3 instead of additional off-post groundwater sampling, which is no longer needed under this project.

TO79 Update:

The status of the task order TO79 (Attachment 6) was discussed.  Other discussion items included LAN support activities, status of encyclopedia updates and the April Quarterly Progress Report.  Action items resulting from the TO79 discussions included:

Action Item:   Parsons to prepare final April Quarterly Progress Report.

TO42 Update:

The status of task order TO42 (Attachment 7) was discussed.  The well installations, groundwater monitoring reports, fact sheets, and the SOP for electronic data management were discussed.  A schedule for the June 2003 groundwater monitoring event was confirmed.  A discussion of whether TO42 electronic data issues can cover LAN support visits occurred.  The remaining wells to be installed under TO 42 were discussed, specifically the schedule, budget issues, and concerns for the off-post well installation to be conducted on the private well owners’ property.  Additional labor costs needed for the well installation activities were discussed and plans to reallocate funds to complete the drilling wbs.  Action items resulting from the TO42 discussions included:

Action Item:   Evaluate budget remaining on the Information Management subtask to determine if LAN support visits can be included. 

Action Item:   Research costs for providing alternate source of drinking water during off-post well installation.

Action Item:   Discuss options for reallocation of funds on the drilling wbs (04) with AFCEE and the contracting officer. 

TO58 Update:

The status of task order TO58 (Attachment 8) was discussed.  The status of each task was discussed in detail, focusing on physical percent complete and remaining activities.  Four TIM meeting remain (one with Ross Miller, technical director), one regulatory support meeting, and two Karst support meetings remain.  One fact sheet also remains.  The topic of the final fact sheet under this task order will present treatability study results.  The schedule for completing the subslab and SVE system treatability study was discussed.  Subslab SVE system testing has been completed, and at least 3-4 more months remain in the AOC-65 SVE treatability study.  The groundwater recharge study is on hold pending approval of sampling Standard Operating Procedures (SOPs) and the actual need for significant rainfall.  Gary Cobb also presented options for telemetry for the weather station to determine if CSSA wanted a system set up on both weather stations, or just the AOC-65 weather station.  Action items resulting from the TO58 discussions included:

Action Item:   Complete draft geophysical test report for distribution to CSSA and AFCEE for review.

Action Item:   Procure telemetry for weather station, and set up system to retrieve the data in real-time.

Action Item:   Finalize DQOs for shallow groundwater recharge study, the associated SOPs, and train sufficient Parsons and CSSA staff  so that a large number of individuals are available to collect samples when rainfall events of sufficient magnitude trigger the need to conduct groundwater samples on short advance notice.

TO0009 Update:

The status of task order TO0009 (Attachment 9) was discussed.  The low water crossing near AOC 55 was completed and preparations are being made to start the sifting  and contaminated soil removal actions.  Concerns were noted  regarding the availability  of UXO technicians due to the Iraq war.  A cost modification was sent to Herminia Ruiz, Contracting Officer, for unexpected field conditions regarding the mechanical sifting of the soils within AOC 55.   Action items resulting from the TO0009 discussions included:

Action Item:   Provide CSSA with a schedule regarding the sifting and removal efforts.

TO 0012 Update:

The status of task order TO0012 (Attachment 10) was discussed.  Schedule of activities were discussed. All efforts  remain for this project and scheduling will need to be coordinated with CSSA and Sanchez (subcontractor installing the bullet trap within Building 90).  Action items resulting from the TO 0012 discussions included:

Action Item:   Coordinate a schedule with CSSA regarding the metal backdrop removal within the East Pasture and removal efforts within Building 90.

Other Topics:

The status of the Archaeology Project (Attachment 11) was briefly discussed.  The Memorandum of Agreement is currently be reviewed by CSSA’s legal staff.  Another topic discussed was the anticipated TO 0019.  An additional action item includes:

Action Item:   Based on recent results of surface soil sampling at SWMU B-8, it is apparent that the extent of surface soil contamination has not been determined.  This site is included in the SOW for the new TO 0019.  CSSA asked that this site be replaced with AOCs 38 and 41 in the proposal since RRS1 closure of SWMU B-8 will require excavation and removal of far more than 250 cubic yards.

Attachment 1:  Agenda for Technical Interchange/Progress Meeting #8

Attachment 2:  RL17 Project Update

Attachment 3:  RL74 Project Update

Attachment 4:  RL53 Project Update

Attachment 5:  RL83 Project Update

Attachment 6:  TO79 Project Update

Attachment 7:  TO42 Project Update

Attachment 8:  TO58 Project Update

Attachment 9:  TO0009 Project Update

Attachment 10:  TO0012 Project Update

Attachment 11:  Archaeology Project Update

Attachment 1 - Agenda for Technical Interchange/Progress Meeting #8

CSSA Environmental Projects

Status Overview and Update

Time:  Thursday, May 1, 2003;  8:30 am to 5:00 pm

Place:  Parsons Office, Austin, Texas

Objectives

  1. Provide financial updates on all active projects (RL17, RL74, RL83, RL53, TO 0042, TO 0058, TO 0079, TO09, TO12).

  2. Discuss status of remaining tasks on all active projects.

  3. Results of latest SWMU/AOC Sampling (B-8, B-34, Bldg 43)

  4. Others??

Time

Topic

8:30am – 12:00 pm

RL17 Update

Summary of SWMU/AOC Status

Burdey, North

RL74 Update

Aerial/LIDAR

Hydro Model Task

Burdey, Griffin, Pearson

 

RL83 Update

B-3 Mod

Burdey, Pearson, Cobb, Vanderglas

 

TO79 Update

Burdey, Riley

12:00pm – 1:00pm

Lunch

 

1:00pm – 2:00pm

TO42 Update

Financial update

Well Installations

Groundwater reports / Data verification

Fact Sheets

SOP – electronic data management

Riley, Burdey

2:00pm – 3:00pm

TO58 Update

Vanderglas

3:00pm – 4:00pm

TO 09 Update

Rice, Burdey

 

TO 12 Update

 

 

RL53 Update

 

4:00pm – 5:00pm

Upcoming projects (Groundwater, SWMU/AOC Closures, Administrative Support)

Burdey, Pearson, Rice

Attachment 2 - RL17 Project Update

Task Name

Completed

To Complete

Outstanding Issues

01:  RFI Scoping

Project plans.

 

Task is complete.

03:  Site Characterization and Field Activities

Field Effort 1 (Mar 95)

Draft Addenda to investigation rpts (B-8, B-34, Bldg 43)

Extent of contamination not yet defined at SWMUs B-8, B-34, Bldg 43

Field Effort ITIR – final

 

Field Effort 2 (Aug 95; May 96)

 

Field Effort 2 ITIR – draft

 

29 of 29 draft & final RFI/Clos. Rpts

 

Final Background Soils report (6/96)

 

05:  O-1 Treatability Study

Bench scale and field scale studies

 

Task is complete.

Draft and final report

 

05010:  B-3 SVE Treatability Study

Installation of additional SVE wells

Final report

Was Nov. 2001 Soil Vapor Extraction Test Report the final?

Multiple configuration testing

 

Data validation and ITIR

 

Draft report

 

08:  Groundwater Monitoring

No groundwater encountered

 

Task is complete.

09:  Sampling and Analysis

Field Effort 1 analysis & data validation

 

Task is complete.

Field Effort 2 analysis & data validation

 

Final analytical ITIR

 

10:  Site Work and Utilities

Completed prior to start of field activities

 

Task is complete.

11:  Meeting Minutes

Kickoff Meeting & Minutes

 

Task is complete.

#2 Meeting & Minutes

 

#3 Meeting & Minutes

 

#4 Meeting & Minutes

 

#5 Meeting & Minutes

 

#6 Meeting & Minutes

 

#7 Meeting & Minutes

 

#8 Meeting & Minutes

 

#9 Meeting & Minutes

 

12:  Presentation Materials, Preparation

Kickoff Meeting materials

 

Task is complete.

#2 Meeting materials

 

#3 Meeting materials

 

#4 Meeting materials

 

#5 Meeting materials

 

#6 Meeting materials

 

#7 Meeting materials

 

#8 Meeting materials

 

#9 Meeting materials

 

13:  Letter Report

SWMU Summary Letter Report

 

Task is complete.

14:  Special Notifications

None required.

 

Task is complete.

15:  Monthly Mgt Reports

90 months of performance.

 

Extension of period of performance to Sept 2003 to be requested.

16:  Contractor Personnel Chart

Contractor Personnel Chart

 

Task is complete.

99:  Integrated Waste Mgt. and Spill Plan Preparation

Draft and final plans

 

Task is complete.

 

 

90:  Program Mgt

90 months of performance

 

 

Extension of period of performance to Sept 2003 to be requested.

RL17 Budget Status (as of April 25, 2003), fee not included

Labor

ODCs

Total

Budget

$1,072,194

$354,808

$1,427,002

Expended

$1,048,307

$325,072

$1,373,378

Remaining

$23,88

$29,736

$53,624

Attachment 3 - RL74 Project Update

Task Name

Completed

To Complete

Outstanding Issues

01:  Project Management

Monthly project mgmt.

Monthly project mgmt.

 

02:  Meetings

Kickoff Meeting & Minutes

 

Task is complete.

TIM #1 Meeting & Minutes

 

TIM #2 Meeting & Minutes

 

TIM #3 Meeting & Minutes

 

TIM #4 Meeting & Minutes

 

TIM #5 Meeting & Minutes

 

03:  Groundwater Sampling & GAC Installation

Apply for Permit Modification

Finalize GAC Manual and distribute

 

Procurement of lab

 

Mar 2000 Groundwater Sampling

 

Mar 2000 Data Validation

 

Mar 2000 Report

 

June 2000 Groundwater Sampling

 

June 2000 Data Validation

 

June 2000 Report

 

04:  Pump Installation

Purchase and Install Pumps

Finalize Pump Installation Report

(included in the Well Installation Rpt)

05:  SVE O&M

Soil Gas Sampling & Analysis

 

Task is complete.

Data Validation

 

SVE O&M Report

 

06:  Plans

Final RFI Work Plans

 

Task is complete.

Final addenda to SAP, HSP

 

Final Waste Analysis Plan

 

Final Interim Measures Work Plan

 

07:  Current Conditions Report

Final Current Conditions Report

 

Task is complete.

08:  Interim Measures

Procurement completed

 

Task is complete.

Drill 25 soil borings

 

Excavate, stabilize & dispose waste

 

Interim Measures Report

 

09:  H Order Support

Meetings/other support re: H order

 

 

10:  Building 40 Sampling

Sampling at Bldg. 40

Wash building floors, collect rinsate

 

Data Validation

Final Closure Report

Draft Closure Report

 

11:  GIS and Web Site

Corrected SWMU locations on maps

Update aerial photography / LIDAR

 

Published schema

 

Transferred data into TSSDS 1.8

 

Created database in SQL server

 

Hyperlinking of Encyclopedia

 

Entered analytical data

 

12:  IDW Management

Dispose of all IDW

 

Task is complete.

13:Groundwater Model Identification and Linking

August 10, 1999, meeting to discuss groundwater modeling issues

 

 

ID of appropriate gw model (GMS)

Link model inputs to GIS

14:  Encyclopedia Updates & Revs

Updates and revisions initiated

 

Task is complete.

15:  Laboratory Audit

(O’Brien & Gere)

Reviewed preliminary data packages

 

Task is complete.

Conducted lab audit

 

Prepared final audit report

 

Submit audit to lab

 

Review/reply to lab response

 

Mid-project QA/QC checks

 

16:  Off-Site Well Sampling

Sampled 3 off-site wells Sept. 99

 

Task is complete.

Data validation

 

Include results in DO23 Report

 

17:  Additional Groundwater Sampling

Sept 2000 Sampling & Reporting

 

Task is complete..

Dec. 2000 Sampling & Reporting

 

Mar. 2001 Sampling & Reporting

 

June 2001 Sampling & Reporting

 

RL74 Budget Status (as of April 25, 2003), not including fee

Labor

ODCs

Total

Budget

$627,153

$470,423

$1,097,577

Expended

$612,792

$313,772

$926,54

Remaining

$14,361

$156,651

$171,013

Attachment 4 - RL53 Project Update

Task Name

Completed

To Complete

Outstanding Issues

01:  Project Management

Monthly project mgmt.

Monthly project mgmt.

 

02:  Site Characterization and Reporting

Field Work and Reporting

SWMU B-10 requires finalizing

Finalize SWMU B-10 Report

03:  Groundwater Well Installation

Install Groundwater Wells

 

Task is complete

04:  Sampling and Analysis

Analytical data validation

 

Task is complete

05:  GIS

Aerial Flyover Image

 

Task is complete.

SDS Data Population

 

06:  Plans

Final RFI Work Plans

 

Task is complete.

Final addenda to SAP

 

Final addenda to HSP

 

07:  Meetings

Kickoff Meeting & Minutes

TIM #1 Meeting & Minutes

TIM #2 Meeting & Minutes

TIM #3 Meeting & Minutes

TIM #4 Meeting & Minutes

 

Task is complete.

09: Background Metals Evaluation

Update Glenrose Background Metals

 

Task is complete

RL53 Budget Status (as of April 25, 2003), not including fee

Labor

ODCs

Total

Budget

$251,295

$101,872

$353,167

Expended

$243,111

$97,273

$340,385

Remaining

$8,184

$4,599

$12,783

Attachment 5 - RL83 Project Update

Task Name

Completed

To Complete

Outstanding Issues

01:  Project Management

 

Monthly project mgmt.

 

02:  Meetings

Kickoff Meeting & Minutes

 

 

TIM #1 Meeting & Minutes

 

TIM #2 Meeting & Minutes

 

TIM #3 Meeting & Draft Minutes

Final minutes

TIM #4 Meeting & Minutes

 

TIM #5 Meeting & Minutes

 

TIM #6 Meeting & Minutes

 

TIM #7 Meeting & Minutes

TIM #8 Meeting & Minutes

03:  Well Research

Initiated Banks Info. Systems records review

 

Task is complete.

Initiated field verification of local wells (Sept 99)

 

TNRCC/SAWS Record Review

 

Site visit/mapping

 

Final Well Research Report

 

04:  Hydrogeologic Conceptual Site Model

Initiated definition of database info.

Finalize cross-sections

 

Implement database/GIS

Finalize structure maps

Define boundaries/approach

Source area proximity relationships

 

Groundwater flow assessment report

05:  SVE O&M

Final work plan addenda (Dec 99)

 

Task is complete.

Procurement

 

Diagnostic check & repair

 

Modify & restart O&M

 

System bi-weekly checks

 

Monitoring visits

 

Final sampling test

 

SVE O&M Assessment Report

 

06:  Risk Assessment Conceptual Site Model Planning

Site visit

 

Task is complete.

ID of potential pathways, receptors

 

Prepared basewide CSM

 

Risk Assessment Tech. Approach

 

07:  Cluster Well Installations

Completed Work Plan addenda

Final Well Installation Report

 

Procurement

 

 

Cluster well installations

 

 

Geophysical logging

 

 

Well development

 

 

Surveying

 

 

Pump installation

 

 

Transducer installation

 

 

Draft Well Installation Report

 

 

08:  Quarterly Progress Reports

Progress Report 1 (August 1999)

 

Task is complete.

Progress Report 2 (November 1999)

 

Progress Report 3 (February 2000)

 

Progress Report 4 (June 2000)

 

Progress Report 5 (August 2000)

 

Progress Report 6 (November 2000)

 

Progress Report 7 (February 2001)

 

Progress Report 8 (June 2001)

 

09:  SWMU and AOC Investigations

Plan addenda

Final SWMU B-23A RFI Report

 

Geophysical surveys (Aug 99)

 

Initiated procurement

 

Drilling and sampling

 

Data validation

 

Draft & Final Reports

 

10:  Soil Pile Disposition Assessment

Sampling & analysis of soil piles

 

 

Contacted labs regarding analysis

 

Draft Assessment Report

Final Assessment Report

 

Treatability Study Report

11:  Encyclopedia Updates

Encyclopedia updates

 

Task is complete.

12:  Title V nonapplicability demonstration

Site visit

 

Task is complete.

Title V Nonapplicability Documentation

 

 

13:SPCC Plan Update

Site survey

 

Task is complete.

Final SPCC Plan Update submitted

 

14:  TPDES Permit Update

Well and landowner research

 

Task is complete.

Initiated wastewater sampling/analysis

 

Soil sampling for land application sites

 

Identified gw wells & locations

 

Data compiled/entered into TNRCC permit application forms

 

Permit Amendment Application

 

15:  Two Laboratory Audits

Reviewed preliminary data packages

 

Task is complete.

Reviewed SOPs

 

Conduct lab #1 audit (APPL, Aug 99)

 

Conduct lab #2 audit (DataChem,Oct99)

 

Prepare final audit reports

 

Submit audits to lab

 

Review/reply to lab responses

 

16:  GIS Enhancements and Database Updates

Initiated planning for field data collection

Continue adding sampling data, hydrogeology data

 

Complete DEM

 

Update of GIS underway

 

LAN administration

 

Air pollution application

 

Enhancements of VB application

 

17:  Groundwater Sampling

Sep 2000 new well sampling

 

Task is complete.

Dec 2000 new well sampling

 

Mar 2001 new well sampling

 

Jun 2001 new well sampling

 

Sep 2001 new well sampling

 

Dec 2001 new well sampling

 

18:  Community Relations Plan

Developed mailing list & info postcards

 

Task is complete.

Conducted interviews

 

Final CRP (Sept 99)

 

RL83 Budget Status (as of April 25, 2003), not including fee

Labor

ODCs

Total

Budget

$1,527,651

$1,355,554

$2,883,205

Expended

$1,298,590

$904,754

$2,203,344

Remaining

$229,061

$450,800

$679,861

Attachment 6 - TO 79 Project Update

Task Name

Activity

Status

Outstanding Issues

01:  Task Order Management

Monthly project mgmt.

Monthly project mgmt.

Ongoing

02:  Meetings

Kickoff Meeting & Minutes

January 29, 2003

Schedule a TIM meeting?

TIM #1 Meeting & Minutes

To be determined

03:  Environmental Ency Updates

Encyclopedia Update, January 2003

Complete

30% complete

Encyclopedia Update, April 2003

To be mailed May 10th

Encyclopedia Update, July 2003

pending

Encyclopedia Update, October 2003

pending

Encyclopedia Update, January 2004

pending

04:  LAN Support

Monthly LAN support visits

complete

100% complete

No-cost modification submitted to remove one quarterly report and add additional LAN support, no comments received from AFCEE.

 

 

05:  Quarterly Progress Reports

Quarter 15, January 2003

Complete

30% complete

Quarter 16, April 2003

Final to be submitted May 10th

Quarter 17, July 2003

pending

Quarter 18, October 2003

pending

Quarter 19, January 2004

Removed, transfer funds to LAN support?

TO 79 Budget Status (as of April 25, 2003)

Labor

ODCs

Total

Budget

$93,516

$5,305

$98,821

Expended

$37,067

$1,703

$38,770

Remaining

$56,449

$3,602

$60,051

Attachment 7 - TO 42 Project Update

Task Name

Activity

Status

Outstanding Issues

01:  Project Management

Monthly project mgmt.

Monthly project mgmt.

Ongoing

02:  Meetings

Kickoff Meeting & Minutes

Done

Schedule a TIM meeting?

TIM #1 Meeting & Minutes

November 15, 2002

TIM #2 Meeting & Minutes

March 20, 2002

TIM #3 Meeting & Minutes

 

TIM #4 Meeting & Minutes

 

TIM #5 Meeting & Minutes

 

TIM #6 Meeting & Minutes

 

03:  Site Survey/Workplans

--

--

Complete

04:  Upgrades/Well Installations

Upgrades to Well G, Well 16 (CS-MW16-LGR), CS-MW1-LGR, CS-MW2-LGR, and Well H

Complete

65% complete

Installation of MW18-LGR, MW19-LGR, MW17-LGR, MW12-CC, MW12-BS, MW12-LGR, MW1-BS, MW1-CC, MW2-CC, MW11-LGR A, MW11-LGR B, MW16-CC

Complete or underway.

Installation of MW13-LGR, MW14-LGR, MW20-LGR, MW21-LGR, (Westbays) and MW2-CC (?)

Pending.

 

Well Installation Report

Pending

 

CSM Update

Pending

05:  On-post Groundwater Monitoring

March 2002

Complete

75 % complete

June 2002

Complete

September 2002

Complete

December 2002

Complete

March 2003

Sampling complete, draft report due May 23rd

June 2003

Pending

 

06:  Analytical Verification/Validation

March 2002

Complete

70% complete.

June 2002

Complete

September 2002

Complete

December 2002

Complete

March 2003

In review

June 2003

pending

07:  Information Management Systems

Master document list

(Ency. updates ongoing)

40% complete

GIS data package; GIS manual update

 

Report of Findings detailing data acceptability

 

Update all data to the SDS database

 

SOP for electronic data

Draft version submitted; Final to be submitted May 2003

08:  Off-post Groundwater Monitoring

September 2002

Complete

80% complete

December 2002

Complete

March 2003

Sampling event complete

June 2003

Pending

TO 42 Budget Status (as of April 25, 2003)

Labor

ODCs

Total

Budget

$1,308,192

$1,615,859

$2,924,051

Expended

$754,426

$626,066

$1,380,492

Remaining

$553,766

$989,793

$1,543,559

Attachment 8 - TO 0058 Project Update

Task Name

Completed

To Complete

Outstanding Issues

01:  Task Order Management

 

 

 

01010:  Management

19 months of management

18 more months of management

 

01020: Status Reports

19 Monthly MPRs

Quarterly Schedule Updates

18 more Monthly MPRs

Quarterly Schedule Updates

 

01030: Karst Expert

Reviewed GVI Karst Investigation

None

Subtask is complete.

01040: Procurement

Drilling subcontract,

3 Lab subcontracts

Geophysical Equip Vendor subcontracts

IDW subcontracts,

 Removal Action subcontracts, and equipment purchases

Government Reporting

Change orders to Lab & Drilling Subcontracts, Tracer Study subcontract, newequipment purchases

 

01050: Modification Proposals

Modification No. 1 & 2 Proposals

Modification No. 3 Proposal

None

Subtask is complete.

02: Meetings & Site Visits

 

 

 

02010 Misc Meetings

Post-award meeting,

Technical Planning meeting,

1.5 DQO meeting(s)

None

Subtask is complete.

02020 TIM/Tech Interchange Mtgs

6 TIMs held

Minutes from TIM 1-5 finalized

4 TIMS remain

TIM 6 minutes finalized

 

02030 Karst & Regulatory Mtgs

1 Regulatory Support meeting held

1 Regulatory Support meeting

2 Karst meetings

 

02040 Public Meetings & Fact Sheets

Public meeting held in October 2002

Fact Sheet 1

Fact Sheet 2

 

03:  Removal Actions

 

 

 

03010: Cleanup Plan Preparation

Cleanup Plan including

Environmental Cleanup Plan

SAP and H&S Plan Addenda

Waste Management Plan Addenda

None

Subtask is complete.

03020: Engineering Bid Package

Prepared Bid Package & Mod 02 Design

Check Construction Detail

Subtask is complete.

03030: Air Permitting Issues

Completed Standard Exemption

Air Permit Modification Issues

 

03040: Subslab Ventilation

Installation & Testing of subslab system

Prepare O&M section of SVE O&M

 

03050: Implement Removal Action

Implemented removal action

Constructed drainage diversion

None

Subtask is complete.

03060: Interim Measures Report

Draft report submitted in March 2003

Finalize report after comment receipt

 

03070: Subslab O&M Activities

Not yet initiated

Conduct O&M of subslab system in coordination with AOC-65 SVE O&M

 

04: Treatability Study

 

 

 

04010: Surface Geophysical Testing

Resistivity Study

2-D Seismic Survey

None

Subtask is complete.

04020: Treatability Test Plan

Treatabilty Test Plan Prepared

None

Subtask is complete.

04030: Groundwater Recharge

Installed 6 piezometers

Installed transducers & weather station

Began data collection

Continue data collection

Begin data interpretation

Install telemetry system

Need significant rainfall events & SOP for data collection.

04040: SVE Study Activities

Installed 7 VMPs & 7 VEWs

Constructed SVE manifold

Initial soil gas radius of influence testing

Continue radius of influence testing

Manage knock-out pot water

 

04050: Miscellaneous Studies

Not yet initiated

Tracer study

Need to define clear objectives and test design for tracer study.

04060: SVE O&M Plan & Activities

Not yet initiated

Prepare O&M Plan

04070: SVE O&M Reporting

Not yet initiated

Prepare O&M Report after 6 months of data collection.

 

05: Technology Evaluation

 

 

 

05010: Technology Evaluation

Prepared Veg-oil/Bark mulch Memo

Prepare position paper from Fractured Media Conference/workshop

 

05020: Geophysical Test Report

Prepared draft Geophysical Test Report

Finalize report upon receipt of comments

 

05030: Interim SVE Report

Not yet initiated

Prepare report after completion of SVE tests.

 

05040: Technology Evaluation Report

Not yet initiated

Prepare report after completion of O&M activities.

 

TO 0058 Budget Status (as of April 25, 2003)

Labor

ODCs

Total

Budget

$957,873

$613,088

$1,570,961

Expended

$765,931

$513,671

$1,279,602

Remaining

$191,942

$99,417

$291,359

Attachment 9 - TO 0009 Project Update

Task Name

Completed

To Complete

Outstanding Issues

90:  Project Management

Monthly project mgmt.

Monthly project mgmt.

 

02:  Planning

Field Work Plans

Finalize plans once modification is received for sifting  SOP and schedule.

 

03:  Field Work

Geophysical investigation

 

Geophysical efforts complete

 

AOC 55 Removal Actions

Requires modification to allow sifting of removed soils for UXO identification and management.

 

 

Low Water Crossing Construction

 

Low water crossing construction complete

04: Reporting

Investigation report

 

Investigation report complete

 

Removal Action completion report

Needs to be completed once removal actions are completed.

 

05:  Meetings

Kickoff Meeting & Minutes

TIM #1 Meeting & Minutes

TIM #2 Meeting & Minutes

TIM #3 Meeting & Minutes

TIM #4 Meeting & Minutes

TIMs #3, #4 are still available

 

TO 0009 Budget Status (as of April 25, 2003), not including fee

Labor

ODCs

Total

Budget

$157,331

$731,270

$888,601

Expended

$124,410

$25,202

$149,612

Remaining

$32,921

$706,068

$738,989

Attachment 10 - TO 0012 Project Update

Task Name

Completed

To Complete

Outstanding Issues

90:  Project Management

Monthly project mgmt.

Monthly project mgmt.

 

02:  Planning

Field Work Plans

Draft and Finalize plans.

 

03:  Field Work

East Pasture Removal action

 

Geophysical efforts complete

 

Building 90 removal actions

Requires modification to allow sifting of removed soils for UXO identification and management.

 

 

Removal Action completion report

Needs to be completed once removal actions are completed.

 

05:  Meetings

Kickoff Meeting & Minutes

Kick off meeting  still available

 

TO 0012 Budget Status (as of April 25, 2003), not including fee

 

Labor

ODCs

Total

Budget

$38,368

$51,125

$89,493

Expended

$3,187

$3

$3,190

Remaining

$35,181

$51,122

$86,303

Attachment 11 - Archaeology Project Update

Task Name

Completed

To Complete

Outstanding Issues

01:  THC Correspondence

Letter to THC, conference calls

 

Task is complete.

02:  LAN Support

LAN Support in March and April

 

Task is complete.

03:  HABS Documentation

Memorandum of Agreement

 

 

 

Level III Documentation

 

Site Plans