Major objective needs to be defined. Some questions to consider are:
Is our only objective to obtain a partial closure on the O-1 pond by removing contaminated soil? If so, soil borings may not be necessary. |
|
If an objective is also to characterize underlying rock strata at the same time as “closing” the O-1 pond soils, then are 25 borings really needed? |
This scenario includes completing 25 soil borings in stages to define extent of contamination by:
Completing up to 25 soil borings to approximately 27 feet below ground surface (bgs) in a radiating pattern out from the historic O-1 pond (Figure 1). |
|
Completing two sets of borings and collecting and analyzing 3 soil samples from each boring. If contamination is found in any sample, then additional borings will be completed beyond the contaminated borings. |
|
Continuing this process until extent is defined or until 25 soil borings are completed. |
Items
to consider:
Completing borings inside the O-1 pond.
Timeliness of analyzing samples.
This scenario includes excavating the contaminated soil from the O-1 pond by:
Overexcavating all soil from the O-1 pond historic boundary until no signs of contamination are detected. |
|
Collecting and analyzing sidewall samples from the excavated area. If contamination is found in any sample, then additional excavation will be completed and additional sidewall samples will be collected. |
|
Continuing this process until all contaminated soils are removed. |
Items
to consider:
Necessity of borings (pathways for contamination).
Timeliness of analyzing samples.
Completing borings inside the O-1 pond.
This scenario includes completing 25 soil borings set out in a grid pattern to define extent of contamination by:
Completing up to 25 soil borings to approximately 27 feet below ground surface (bgs), set out in 10 foot by 10 foot grids (Figure 2). |
|
Creating 10 ft by 10 ft grids, starting in the historic O-1 pond area, completing one boring for each grid, and collecting and analyzing 3 soil samples from each boring. If contamination is found in any sample, then additional grids and borings will be completed beyond the contaminated boring. |
|
Continuing this process until extent is defined or until 25 soil borings are completed. |
Items
to consider:
Completing borings inside the O-1 pond.
Timeliness of analyzing samples.