Health and Safety Plan - TO 0009 AOC 55 Remedial Action, June 2003
Table of Contents
|
Name |
Date |
Approved By Project Manager: |
Ken Rice |
June 17, 2003 |
This addendum provides additional information to the Health and Safety Plan for the Closure of Solid Waste Management Units at Camp Stanley Storage Activity (Volume 1-5 of the Environmental Encyclopedia).1 The purpose of this addendum is to describe safe practices for work to be performed during the AOC 55 Remedial Actions under task order 0009. An additional comprehensive safety plan will be generated to incorporate construction and UXO avoidance activities for all on-site personnel, including Parsons Personnel, subcontractors and CSSA workers.
1.2 Site History and Description
Section 2 - Safety and Health Risk Analysis
2.2.3 Snake and Africanized Bee Hazards
2.2.6 Chiggers and Ticks Hazards
2.2.8 Utilities and Electrical Hazards
Section 3 - Personnel Protection and Monitoring
3.1 General Safety Training Requirements
3.4 Personal Protective Equipment and Action Levels
3.4.3 PPE and Equipment Decontamination Procedures
3.5 Low and Medium Priority SWMU
Section 4 - Site Control Measures, Accident Prevention, and Contingency Plan
4.2 Site Organization-Operation Zone
Plan Addendum Acceptance Form - Summary of Activities
Table
Table 2.1 Toxicological Properties of Compounds
[1] Parsons, 1995. Health and Safety Plan for Closure of Solid Waste Management Units at Camp Stanley Storage Activity, prepared under Air Mobility Command Contract F11623-94-D0024, Order RL17, prepared by Parsons Engineering Science, Inc., Austin, Texas, December 1995.