Activity |
Objectives |
Action |
Objective
Attained? |
Recommendations |
|
Objective 1: Meet TNRCC Requirements for Site Closure |
|||||
Attainment of Risk Reduction Standard Number 1: Closure/Remediation to Background |
|||||
|
Remove all hazardous and non-hazardous waste and
waste residues and contaminated design and operating system components such
as liners, leachate collection systems, and dikes from the unit or area of
the unauthorized discharge. For remediation of media that have become
contaminated by releases from a waste management unit or by other
unauthorized discharge of hazardous or non-hazardous waste, the contaminated
media must be removed or decontaminated to cleanup levels specified in this
section (30 TAC 335.554(b) and (c)). |
Surface soil sampling were collected under
Building 90 and soil borings were advanced in and around Building 90. Samples were analyzed for metals, VOCs,
and, in some cases, SVOCs and TPH.
|
No.
Reported TCE concentrations exceeded RRS1 closure concentrations for
soil samples collected at borings advanced near the drainage line that runs
from the vats inside Building 90 to the drainage ditch. The borings for which TCE SQLs are
exceeded lie within the confines of the TCE plume identified in the soil gas
survey.
|
Further work is needed to characterize the
migration characteristics of TCE around AOC65 and to characterize the extent of contamination around SB03.
|
|
|
Determine compliance with RRS1 closure
requirements by comparing to background as represented by results of analyses
of samples taken from media that are unaffected by waste management or
industrial activities. If the practical quantitation limit (PQL) is greater
than background, then the PQL rather than background shall be used as the
cleanup level provided that the person satisfactorily demonstrates to the
executive director that lower levels of quantitation of a contaminant are not
possible (30 TAC 335.554(d)). |
Contaminant concentrations were compared to second
revised background levels (Parsons, February 2002) or RLs, which are
equivalent to PQLs. |
No. Not
all results were below background metals levels or RLs, as described above. |
Further work is recommended. See above. |
|
|
Attainment of cleanup levels shall be demonstrated by collection and
analysis of samples from the media of concern (30 TAC 335.554(e)). |
Surface and subsurface samples were collected at the site and
analyzed for contaminants of potential concern, including metals, VOCs,
SVOCs, and TPH.
|
No. See above. |
Further work is recommended.
See
above. |
|
Objective 2: Meet Requirements of 3008(h) Order for RFI |
|||||
RFI Workplan Requirements |
|||||
Field Sampling
(Detailed
listing of methods and procedures are provided in project plans which are
incorporated by reference). |
Conduct field sampling in accordance with procedures defined in the
project work plan, SAP, QAPP, and HSP. |
All sampling was conducted
in accordance with the procedures described in the project plans. |
Yes. |
NA |
|
Facility Investigation |
|||||
Characterization of Environmental Setting - Hydrogeology (B.3.A.1) |
Evaluate hydrogeologic conditions at the site.
|
Not included in this phase of the RFI at AOC 65. Groundwater of the Trinity
Aquifer is being addressed through the Groundwater Investigation. |
NA |
NA |
|
Characterization of Environmental
Setting- Soils (B.3.A.2) |
Characterize soils in accordance with USCS soil classification system
(B.3.A.2(a)). |
Soil types at the site are
based on the SCS Bexar County Soil Survey (USDA, 1991) and are described in
Section 1.2.1.
|
Yes. |
NA |
|
Determine soil pH (B.3.A.2(e)). |
The pH of each of the soil
types evaluated as part of the background metals concentration study was
determined through laboratory analysis.
According to those analyses, the pH of Crawford and Bexar Complex
soils is 7.77. |
Yes. |
NA |
||
Determine moisture content (B.3.A.2(g)). |
The moisture content of
each sample was analyzed and reported in the laboratory package.
|
Yes. |
NA |
||
Characterization of
Environmental Setting – Surface Water and Sediment (B.3.A.3) |
Characterize marshes, creeks, wetland areas, or ditches at the site. |
No marshes, creeks, or
wetland areas are present at the site.
A ditch is located approximately 50 feetwest of AOC 65. Direction of runoff flow has been
evaluated in Section 1.2.1.
|
Yes. |
NA |
|
Source Characterization (B.3.B) |
Identify the source area (B.3.B.1). |
A description of the
potential source area is provided in Section 1.1.2.2. |
Yes. Sampling at the site was biased toward
areas most suspected of contamination.
|
NA |
|
|
Identify the location of the unit/disposal area (B.3.B.2(a)). |
The boundaries were
initially marked from review of CSSA records, and confirmed by field
investigations. |
Yes. Although the accuracy of the boundary
survey of the site is estimated to have an approximate error of 25 feet, this
accuracy is sufficient for closure under RRS1. |
NA |
|
|
Identify the type of unit/disposal area (B.3.B.2(b)). |
A
drainage line was identified that ran from Building 90 to a drainage ditch.
|
Yes. A soil gas survey, surface and subsurface
sampling were performed. The TCE
plume identified by the soil gas survey was confirmed, but the lateral and
vertical extent were not defined. |
Further work is recommended. See above. |
|
|
Identify design features (B.3.A.2(c)). |
All available information
regarding the design of the site is provided in Section 1.1. |
Yes. All investigation evidence indicates that
the vat in Building 90 was used to store liquid solvents for cleaning
ordnance.
|
NA |
|
|
Identification of past and present operating practices, period of
operation, age of unit/disposal area, and method used to close the
unit/disposal area (B.3.B.2(d), (e), (f), and (h)). |
All known information
regarding these items is provided in Section 1.1.2.1. This information is from records review,
interviews, aerial photo review, and visual observations. |
Yes. To the extent possible with data available. |
NA |
|
|
Determine general physical conditions of the site (B.3.B.2(g)) |
The general physical
condition of the site was determined during the field investigation. This information is presented in Section
1.1.2.3. |
Yes. |
NA |
|
|
Identify waste characteristics, including type of waste placed in the
unit, physical and chemical characteristics of the wastes, and migration and
dispersal characteristics of the waste (B.3.B.3). |
Records regarding historic
waste disposal practices at CSSA are very limited. All known information, derived from the Environmental
Assessment (if appropriate for your site), records review, interviews, and
visual observations at the site is provided in Section 1.3. |
Yes. To the extent possible with the data available. |
NA |
|
Contamination
Characterization – Groundwater (B.3.C.1) |
Characterize the vertical and horizontal extent of groundwater
contamination. |
Groundwater samples were
collected at AOC 65. TCE was
identified in excess of its RL in all samples collected.
|
No. |
Further work is recommended. See above. |
|
Contamination
Characterization – Soil (B.3.C.2) |
Determine vertical and horizontal extent of contamination
(B.3.C.2(a)). |
Surface and subsurface soil samples were collected to determine horizontal extent of contamination, if any. |
In most areas, TCE was
detected only in soils, and not in bedrock.
Around the drainage line, however, TCE was detected in the bedrock.
|
Further work is recommended. See above. |
|
|
Describe soil properties (B.3.C.2(c)). |
See “Characterization of
Environmental Setting – Soils” above. |
NA |
NA |
|
|
Identify the direction of contaminant movement (B.3.C.2(d)). |
Contaminant movement
appears to be in the soils, in a south-southwest direction. |
NA |
NA |
|
|
Extrapolate future contaminant movement (B.3.C.2(e)). |
Soil boring and
groundwater samples were collected at AOC 65.
|
Samples collected at AOC
65 exceeded closure criteria for PCE, and, in some locations, other COCs. |
Further work must be done
to clarify the mobility of the COCs. |
|
|
Implement a soil boring investigation to determine the extent of soil
contamination. Soil gas monitoring
will be performed during drilling of all borings. Laboratory analysis of borings for contaminants of potential
concern will be performed on soils at depths where either visual
contamination is evident, or soil gas concentrations indicate
contamination. All boreholes shall be
properly abandoned. |
Soil borings were advanced
in and around Building 90. Soil gases
were monitored during boring collection, and laboratory analyses were
performed on samples retained from portions of the borings that appeared, via
PID measurements, to potentially contain COCs.
|
Yes. |
Further work is
recommended. See above.
|
|
|
Prepare a map of all areas included in the investigation (B.3.C.2(i)). |
Figures included in this
report show all areas included in the investigation.
|
Yes. |
NA |
|
|
All reporting limits should be below regulatory criteria. |
RLs were approved by TNRCC
on October 5, 1999. RLs are
considered RRS1 standards for all analytes except metals.
|
Yes. |
NA |
|
|
Perform all analyses in accordance with the AFCEE QAPP. |
All analyses were
performed in accordance with the AFCEE QAPP and approved variances.
|
Yes. |
NA |
|
|
All data flagged with “U,”
“F,” “M,” and “J” are considered usable for site characterization purposes. |
Yes. |
NA |
||
Contaminant
Characterization – Sediment and Surface Water (B.3.C.3) |
Conduct a surface water and sediment investigation to characterize
contamination resulting from releases at the Facility. |
AOC 65 is located 50 feet
east of a ditch. This ditch only
contains water during and shortly after heavy precipitation. Therefore, surface water was not sampled
as part of the AOC 65 investigation. |
NA |
NA |
|
Potential Receptors
(B.3.D). |
Collect the information necessary to describe the human populations
and environmental systems that are susceptible to contaminant exposure from
the Facility. |
Information regarding
receptors is provided in the Risk Assessment Technical Approach Document
(Volume 1-6). In addition, the Well
Research Report identifies private groundwater users within 0.25-mile and
public water suppliers within 0.5-mile of CSSA |
Yes. |
NA |