Area of Concern 39

Chronology of Actions/Investigations

Year

Month

Action/Results

Action performed by

Project Number

1995

May

Geophysical survey was conducted at all the “open” areas within a 2,000-foot radius of well 16, including AOC 39. Found two anomalies that do not correspond to any surface features/known power lines.

Parsons ES

Order 67

1995

June-July

Nine soil-gas survey samples collected and analyzed for chlorinated and aromatic volatile organics. PCE was the only target analyte detected.

Parsons ES

Order 67

2000

January

Collected five surface soil samples (SS1-5) and analyzed for PCE, TCE and DCE.

Parsons ES
O’Brien & Gere

DO5068

2002

May

Final RCRA Facility Investigation/Closure Report submitted.

Parsons

NA

2002

September

TCEQ issued approval of site closure.

TCEQ

NA